Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Larsen & Toubro Ltd | 20065719 | Gariyava multi village water supply scheme | 250.54 | 164.78 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | No | 0 | NA | No | 14434.00 | 14400.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | SRINGVERPUR DHAM | GARIYAVA | 431675 | GARIYAVA | 93 | 64 | 69 | Work In Progress | Not Certified |
| 2 | Prayagraj | SRINGVERPUR DHAM | GARIYAVA | 431676 | BHITIPATTIBISNIURF BHAGAWANPUR | 72 | 59 | 82 | Work In Progress | Not Certified |
| 3 | Prayagraj | SRINGVERPUR DHAM | GARIYAVA | 431677 | ABDULLAPUR | 140 | 125 | 89 | Work In Progress | Not Certified |
| 4 | Prayagraj | SRINGVERPUR DHAM | GARIYAVA | 431678 | CHANDPUR | 51 | 20 | 39 | Work In Progress | Not Certified |
| 5 | Prayagraj | SRINGVERPUR DHAM | GARIYAVA | 431679 | GOSHPUR | 74 | 70 | 95 | Work In Progress | Not Certified |