Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Fatehpur Gayatri Projects LTD 20065932 Sarai Shahjada 221.53 85.22 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 18 18 Yes 0 NA No 8135.00 7954.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Fatehpur Teliyani Sarai Shahjada 427794 Sarai Shahijada 190 34 18 Work In Progress Not Certified
2 Fatehpur Teliyani Sarai Shahjada 427795 Beni Harsinghpur 175 175 100 Har Gar Jal Not Certified