Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Raebareli Vindhya-GAJA (JV) 20065955 PUKH NAIN Water Supply Scheme 343.87 229.54 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 1 23 23 Yes 0 NA No 17489.00 17389.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Raebareli Diha Pukh Nain 417707 Pukh Nain 246 223 91 Work In Progress Not Certified
2 Raebareli Diha Pukh Nain 417708 Dhan Kesara 113 113 100 Har Gar Jal Not Certified
3 Raebareli Diha Pukh Nain 417709 Gangapur Kamwan 183 147 80 Work In Progress Not Certified