Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20066281 | KALYANPUR VILLAGE WATER SUPPLY SCHEME | 236.35 | 115.52 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 12380.00 | 9131.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Kalyan Pur | 469814 | Chak Chamrauti | 67 | 31 | 46 | Work In Progress | Not Certified |
| 2 | Jaunpur | Mariyahun | Kalyan Pur | 469815 | Chak Sihora | 30 | 11 | 37 | Work In Progress | Not Certified |
| 3 | Jaunpur | Mariyahun | Kalyan Pur | 469816 | Phulwari | 25 | 16 | 64 | Work In Progress | Not Certified |
| 4 | Jaunpur | Mariyahun | Kalyan Pur | 469817 | Kalyanpur | 148 | 128 | 86 | Work In Progress | Not Certified |