Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20068180 | Pahadpur Village water supply scheme | 399.17 | 191.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 26494.00 | 24578.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Machhlishahr | Paharpur | 469525 | Paharpur | 155 | 145 | 94 | Work In Progress | Not Certified |
| 2 | Jaunpur | Machhlishahr | Paharpur | 469526 | Jalalabad | 69 | 58 | 84 | Work In Progress | Not Certified |
| 3 | Jaunpur | Machhlishahr | Paharpur | 469527 | Mirzapur | 71 | 62 | 87 | Work In Progress | Not Certified |
| 4 | Jaunpur | Machhlishahr | Paharpur | 469528 | Nikamuddinpur | 129 | 123 | 95 | Work In Progress | Not Certified |