Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20068487 | Sarai Mohiuddenpur | 533.92 | 170.10 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 37 | 37 | No | 0 | NA | No | 22363.00 | 19976.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Suithkala | Jahooruddinpur | 468245 | Bhatauli | 142 | 130 | 92 | Work In Progress | Not Certified |
| 2 | Jaunpur | Suithkala | Jahooruddinpur | 468246 | Jahooruddinpur | 230 | 230 | 100 | Har Gar Jal | Not Certified |
| 3 | Jaunpur | Suithkala | Haamzapur | 468295 | Baniya Bandh | 3 | 2 | 67 | Work In Progress | Not Certified |
| 4 | Jaunpur | Suithkala | Sarai Mohiuddenpur | 468297 | Sarai Mohiuddenpur | 352 | 336 | 95 | Work In Progress | Not Certified |