Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | NCC Ltd. | 20068739 | BINOODPUR + BIRAIMPUR + AMHIRA GRAM PANCHAYAT WATER SUPPLY SCHEME | 670.84 | 223.71 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 3 | 3 | 3 | 3 | 2 | 0 | 0 | 10 | 10 | Yes | 0 | NA | No | 26210.00 | 16260.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | Bewar | Amhira | 400511 | Amhira | 277 | 275 | 99 | Work In Progress | Not Certified |
| 2 | Mainpuri | Bewar | Amhira | 400512 | Naurangabad | 97 | 96 | 99 | Work In Progress | Not Certified |
| 3 | Mainpuri | Bewar | Amhira | 400513 | Bakipur | 80 | 79 | 99 | Work In Progress | Not Certified |
| 4 | Mainpuri | Bewar | Binodpur | 400520 | Binodpur | 353 | 348 | 99 | Work In Progress | Not Certified |
| 5 | Mainpuri | Bewar | Biraimpur Satdhara | 400521 | Biraimpur Satdhara | 239 | 238 | 100 | Work In Progress | Not Certified |
| 6 | Mainpuri | Bewar | Biraimpur Satdhara | 400522 | Takharau Jiwanpur | 136 | 132 | 97 | Work In Progress | Not Certified |
| 7 | Mainpuri | Bewar | Biraimpur Satdhara | 400523 | Apoor Pur | 113 | 111 | 98 | Work In Progress | Not Certified |