Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lucknow | NCC Ltd. | 20070377 | Bakhtiyar Nagar & Barhi Garhi | 537.87 | 264.53 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 35 | 0 | NA | 0 | NA | No | 16566.00 | 16566.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lucknow | Malihabad | Bakhtiyar Nagar | 415497 | Bakhtiyar Nagar | 490 | 490 | 100 | Har Gar Jal | Not Certified |
| 2 | Lucknow | Malihabad | Bakhtiyar Nagar | 415498 | Bari Jalalpur | 48 | 48 | 100 | Har Gar Jal | Not Certified |
| 3 | Lucknow | Malihabad | Barhi Garhi | 415499 | Barhi Garhi | 336 | 331 | 99 | Work In Progress | Not Certified |
| 4 | Lucknow | Malihabad | Barhi Garhi | 415500 | Kukura | 75 | 67 | 89 | Work In Progress | Not Certified |