Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20074482 | DEVERA GANJ BARAR GP wss | 139.92 | 72.35 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 13 | 13 | Yes | 0 | NA | No | 2237.00 | 2237.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Dubaulia | Devara Ganj Barar | 450433 | Bhatiha | 14 | 13 | 93 | Work In Progress | Not Certified |
| 2 | Basti | Dubaulia | Devara Ganj Barar | 450434 | Para | 76 | 75 | 99 | Work In Progress | Not Certified |
| 3 | Basti | Dubaulia | Devara Ganj Barar | 450435 | Dasharathpur | 8 | 7 | 88 | Work In Progress | Not Certified |
| 4 | Basti | Dubaulia | Devara Ganj Barar | 680632 | Matiha | 14 | 14 | 100 | Har Gar Jal | Not Certified |
| 5 | Basti | Dubaulia | Devara Ganj Barar | 693759 | DEWARA GANGWARAR | 170 | 170 | 100 | Har Gar Jal | Not Certified |