Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Basti VSA 20075419 DHARAM NAGAR & HARI GAON GP wss 451.64 290.75 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
5 1 1 1 1 1 1 0 30 30 Yes 0 NA No 28010.00 23100.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Basti Paras Rampur Hari Gaon 449100 Hari Gaon 418 417 100 Work In Progress Not Certified
2 Basti Paras Rampur Dharm Nagar 449150 Dharam Nagar 109 108 99 Work In Progress Not Certified
3 Basti Paras Rampur Dharm Nagar 449151 Pipari Pokhar 39 30 77 Work In Progress Not Certified
4 Basti Paras Rampur Dharm Nagar 449152 Bhojpur 50 34 68 Work In Progress Not Certified
5 Basti Paras Rampur Dharm Nagar 449153 Sekhui 30 21 70 Work In Progress Not Certified