Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Moradabad | LC INFRA | 20078890 | MOHAMMADPUR DHYAN SINGH MVWSS | 280.07 | 220.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 10879.00 | 10100.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Chhajlet | Mohammadpur Dhyansingh | 388076 | Jewadi | 77 | 1 | 1 | Work In Progress | Not Certified |
| 2 | Moradabad | Chhajlet | Mohammadpur Dhyansingh | 388077 | Jebara | 145 | 140 | 97 | Work In Progress | Not Certified |
| 3 | Moradabad | Chhajlet | Mohammadpur Dhyansingh | 388078 | Mohammadpur Dhyansingh | 260 | 249 | 96 | Work In Progress | Not Certified |