Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kasganj | PNC-SPML-JV | 20083485 | KHITAULI | 258.46 | 93.46 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 16 | NA | 0 | NA | No | 8824.00 | 8824.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kasganj | Sahawar | Khitauli | 398826 | Khitauli | 492 | 306 | 62 | Work In Progress | Not Certified |
| 2 | Kasganj | Sahawar | Khitauli | 398827 | Saiti | 78 | 1 | 1 | Work In Progress | Not Certified |
| 3 | Kasganj | Sahawar | Khitauli | 398828 | Sahawar | 78 | 4 | 5 | Work In Progress | Not Certified |