Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20085078 | GAYAJEETPUR & MUNDULWA GP wss | 268.44 | 130.64 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 16 | 16 | Yes | 0 | NA | No | 13508.00 | 12500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Mundulwa | 449535 | Mundulwa | 141 | 122 | 87 | Work In Progress | Not Certified |
| 2 | Basti | Gaur | Gayajeetpur | 449536 | Gayajitpur | 85 | 72 | 85 | Work In Progress | Not Certified |
| 3 | Basti | Gaur | Gayajeetpur | 449537 | Bairi Khala | 64 | 51 | 80 | Work In Progress | Not Certified |