Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20085086 | CHANDAPALIYA GP wss | 262.16 | 103.77 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 12410.00 | 11500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Vikramjot | Chandapaliya | 450022 | Panderiya | 81 | 80 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Vikramjot | Chandapaliya | 450023 | Raidaspur | 39 | 21 | 54 | Work In Progress | Not Certified |
| 3 | Basti | Vikramjot | Chandapaliya | 450024 | Chandapaliya | 139 | 133 | 96 | Work In Progress | Not Certified |
| 4 | Basti | Vikramjot | Chandapaliya | 450025 | Bhausiya | 15 | 8 | 53 | Work In Progress | Not Certified |
| 5 | Basti | Vikramjot | Chandapaliya | 450026 | Bara Gaon | 6 | 4 | 67 | Work In Progress | Not Certified |