Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20089110 | Safipur Heera and Shahnagar Water Supply Scheme | 374.35 | 223.08 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 31 | Yes | 0 | NA | No | 11854.00 | 11284.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Haldaur | Shahnagar | 386210 | Shahnagar | 330 | 330 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Haldaur | Shahnagar | 386211 | Khalilpur | 20 | 11 | 55 | Work In Progress | Not Certified |
| 3 | Bijnor | Haldaur | Shahnagar | 386212 | Nawajispur Ahamad | 38 | 18 | 47 | Work In Progress | Not Certified |
| 4 | Bijnor | Haldaur | Safipur Heera | 386288 | Safipur Heera | 233 | 233 | 100 | Har Gar Jal | Not Certified |
| 5 | Bijnor | Haldaur | Safipur Heera | 386289 | Mahamoomadpur Haidar | 16 | 16 | 100 | Har Gar Jal | Not Certified |
| 6 | Bijnor | Haldaur | Safipur Heera | 386290 | Govardhanpur Nangli | 161 | 161 | 100 | Har Gar Jal | Not Certified |