Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20090564 | AKARI GP wss | 193.35 | 106.07 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 17 | 17 | Yes | 0 | NA | No | 11132.00 | 10910.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Bahadurpur | Akari | 451577 | Akari | 113 | 112 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Bahadurpur | Akari | 451578 | Bajepur | 45 | 42 | 93 | Work In Progress | Not Certified |
| 3 | Basti | Bahadurpur | Akari | 451579 | Sahupar | 25 | 24 | 96 | Work In Progress | Not Certified |
| 4 | Basti | Bahadurpur | Akari | 451580 | Raine | 89 | 88 | 99 | Work In Progress | Not Certified |