Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20092222 | DARAV NAGAR & MUHIUDDIN NAGAR | 313.58 | 147.51 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 10386.00 | 10386.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Salarpur | Darav Nagar | 401849 | Darav Nagar | 252 | 252 | 100 | Har Gar Jal | Not Certified |
| 2 | Budaun | Salarpur | Muhiuddin Nagar | 401850 | Muhiuddin Nagar | 174 | 174 | 100 | Har Gar Jal | Certified |