Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20092281 | tikari pukhta water supply scheme | 126.34 | 56.03 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 25 | NA | No | 5678.00 | 5000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Usawan | Tikari Pukhta | 402548 | Tikari Pukhta | 155 | 155 | 100 | Har Gar Jal | Certified |
| 2 | Budaun | Usawan | Tikai Pukhta | 402549 | Tikai Pukhta | 113 | 113 | 100 | Har Gar Jal | Certified |
| 3 | Budaun | Usawan | Tikai Pukhta | 402551 | TIKAI KHAM | 43 | 43 | 100 | Har Gar Jal | Certified |
| 4 | Budaun | Usawan | Tikari Pukhta | 402558 | Bachheli Tarachand | 38 | 38 | 100 | Har Gar Jal | Certified |