Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 20093054 | Gopalpur-Hathni Khas Water Supply Scheme | 360.74 | 130.46 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 0 | 0 | 0 | 1 | 1 | 0 | 21 | 21 | No | 0 | NA | No | 22531.00 | 10.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Mankapur | Gopalpur | 445969 | Gopalpur | 107 | 102 | 95 | Work In Progress | Not Certified |
| 2 | Gonda | Mankapur | Gopalpur | 445970 | Kuli Bankat | 67 | 62 | 93 | Work In Progress | Not Certified |
| 3 | Gonda | Mankapur | Gopalpur | 445971 | Turkailee | 104 | 99 | 95 | Work In Progress | Not Certified |
| 4 | Gonda | Mankapur | Gopalpur | 445972 | Ghurahu Jot | 50 | 46 | 92 | Work In Progress | Not Certified |
| 5 | Gonda | Chhapia | Hathni Khas | 446173 | Hathni Khas | 138 | 133 | 96 | Work In Progress | Not Certified |
| 6 | Gonda | Chhapia | Hathni Khas | 446174 | Bhopatpur | 119 | 114 | 96 | Work In Progress | Not Certified |