Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | GA INFRA-VPL | 20093753 | SARAI GANGAPABBI & BHOPAURA GRAM PANCHAYAT WATER SUPPLY SCHEME | 305.64 | 186.51 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | NA | 0 | NA | No | 21107.00 | 21000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Badraon | Bhopaura | 465211 | Bhopaura | 128 | 125 | 98 | Work In Progress | Not Certified |
| 2 | Mau | Badraon | Bhopaura | 465212 | Reuridih | 109 | 104 | 95 | Work In Progress | Not Certified |
| 3 | Mau | Badraon | Sarai Gangapabbi | 465215 | Sarai Gangapalli | 194 | 194 | 100 | Har Gar Jal | Not Certified |