Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20095136 | Lidhaura PWS | 300.69 | 171.11 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 1 | 1 | 1 | 0 | 0 | 60 | 60 | Yes | 0 | NA | No | 32890.00 | 9300.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Achhalda | Lidhaura | 420368 | Makrandpur Phaphoond | 155 | 150 | 97 | Work In Progress | Not Certified |
| 2 | Auraiya | Achhalda | Paitua | 420369 | Purwa Chandraman | 65 | 61 | 94 | Work In Progress | Not Certified |
| 3 | Auraiya | Achhalda | Paitua | 420371 | Purwa Dhamoo Phaphoond | 36 | 31 | 86 | Work In Progress | Not Certified |
| 4 | Auraiya | Achhalda | Lidhaura | 420373 | Lidhora | 138 | 127 | 92 | Work In Progress | Not Certified |