Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | KLSR - RAYS (JV) | 20095770 | SAMAUDDINPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 239.34 | 141.16 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 20 | 20 | Yes | 0 | NA | No | 14077.00 | 11543.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ranipur | Samauddinpur | 466206 | Samauddinpur | 131 | 128 | 98 | Work In Progress | Not Certified |
| 2 | Mau | Ranipur | Samauddinpur | 466207 | Sawanipur | 11 | 9 | 82 | Work In Progress | Not Certified |
| 3 | Mau | Ranipur | Samauddinpur | 466208 | Prema Patti | 5 | 3 | 60 | Work In Progress | Not Certified |
| 4 | Mau | Ranipur | Samauddinpur | 466209 | Katghar Kayam | 67 | 61 | 91 | Work In Progress | Not Certified |
| 5 | Mau | Ranipur | Samauddinpur | 466210 | Nasiruddinpur | 76 | 72 | 95 | Work In Progress | Not Certified |
| 6 | Mau | Ranipur | Samauddinpur | 466211 | Hasanbad | 41 | 37 | 90 | Work In Progress | Not Certified |
| 7 | Mau | Ranipur | Samauddinpur | 466329 | Nizampur Mu. Karmi | 16 | 13 | 81 | Work In Progress | Not Certified |