Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Power Mech Projects Ltd | 20095847 | KAPILMAIYKE KISHUNPUR KAPILE, MANGALPUR TAKAULI | 446.60 | 173.65 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 25 | Yes | No | 17213.00 | 17200.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Amauli | Kapilmaiyke Kishunpur Kapile | 427524 | Kapilmaiyke Kishunpur Kapile | 734 | 608 | 83 | Work In Progress | Not Certified |
| 2 | Fatehpur | Amauli | Mangalpur Takauli | 427581 | Mangalpur Takauli | 193 | 82 | 42 | Work In Progress | Not Certified |