Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | JAKSON - VISHVARAJ (JV) | 20096391 | TENUI AND JUNAYANIYA GP WSS | 379.18 | 95.05 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | Yes | 0 | NA | No | 14639.00 | 14600.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Bhanwapur | Judawaniya | 447881 | Junayaniya | 127 | 126 | 99 | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Bhanwapur | Tenui | 447883 | Tanduai | 115 | 114 | 99 | Work In Progress | Not Certified |
| 3 | Siddharth Nagar | Bhanwapur | Tenui | 447884 | Sultanpur Urf Chandan Joot | 97 | 78 | 80 | Work In Progress | Not Certified |
| 4 | Siddharth Nagar | Bhanwapur | Judawaniya | 447885 | Kohal Goan Coat | 35 | 18 | 51 | Work In Progress | Not Certified |
| 5 | Siddharth Nagar | Bhanwapur | Tenui | 447886 | Nahtuya | 65 | 47 | 72 | Work In Progress | Not Certified |