Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20097037 | CHAURA DHEER PATTI | 552.91 | 344.17 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | NA | 25 | NA | No | 14884.00 | 15355.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Padrauna | Harka Ghurmal | 457887 | Harka Ghurmal | 272 | 272 | 100 | Har Gar Jal | Not Certified |
| 2 | Kushi Nagar | Padrauna | Harka Ghurmal | 457888 | Harka Baijnath Mal | 89 | 89 | 100 | Har Gar Jal | Not Certified |
| 3 | Kushi Nagar | Padrauna | Harka Ghurmal | 457889 | Harka Hanmantgir | 60 | 60 | 100 | Har Gar Jal | Not Certified |
| 4 | Kushi Nagar | Padrauna | Harka Ghurmal | 457890 | Hirnaha | 143 | 143 | 100 | Har Gar Jal | Not Certified |
| 5 | Kushi Nagar | Padrauna | Chaura Khas | 457892 | Chaura Khas | 365 | 365 | 100 | Har Gar Jal | Not Certified |
| 6 | Kushi Nagar | Padrauna | Chauradheer Patti | 457893 | Chauradheer Patti | 329 | 329 | 100 | Har Gar Jal | Not Certified |