Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | GVPR | 20097752 | Raisepur MVS | 484.38 | 226.18 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 18718.00 | 14070.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Mohammadabad | SIKANDER PUR | 418583 | Sikander Pur | 154 | 120 | 78 | Work In Progress | Not Certified |
| 2 | Farrukhabad | Mohammadabad | Raisey Pur | 418618 | Raisey Pur | 286 | 263 | 92 | Work In Progress | Not Certified |
| 3 | Farrukhabad | Mohammadabad | JAIT PUR | 418619 | Jait Pur | 189 | 186 | 98 | Work In Progress | Not Certified |
| 4 | Farrukhabad | Mohammadabad | SIKANDER PUR | 656278 | gazipur | 66 | 66 | 100 | Har Gar Jal | Not Certified |
| 5 | Farrukhabad | Mohammadabad | JAIT PUR | 656356 | Atanpur Nawada | 64 | 64 | 100 | Har Gar Jal | Not Certified |