Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lucknow | NCC Ltd. | 20099816 | Meethenagar Water Supply Scheme | 446.72 | 189.92 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 15259.00 | 15259.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lucknow | Malihabad | Meethenagar | 415525 | Meethenagar | 195 | 195 | 100 | Har Gar Jal | Not Certified |
| 2 | Lucknow | Malihabad | Meethenagar | 415526 | Dugauli | 171 | 167 | 98 | Work In Progress | Not Certified |