Scheme Details
DISTRICT
Pratapgarh
AGENCY
JMC - Kalpataru
SCHEME ID
20099889
SCHEME NAME
Lakhapur Water Supply Scheme
ESTIMATED COST
175.19
EXPENDITURE
25.26
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6991.00
Meter
Length Laid
1000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Mandhyatha | Lakhapur | 429997 | Lakhapur | 247 | 191 | 77% | Work In Progress | Not Certified |