| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20101446 | Seluamau Jahanpur jjm scheme | 256.90 | 130.21 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 14 | 14 | Yes | 0 | NA | No | 13655.00 | 13655.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Rampur Mathura | Jahanpur | 411538 | Deo Ria | 67 | 58 | 87 | Work In Progress | Not Certified |
| 2 | Sitapur | Rampur Mathura | Jahanpur | 411539 | Jahanpur | 23 | 23 | 100 | Har Gar Jal | Not Certified |
| 3 | Sitapur | Rampur Mathura | Jahanpur | 411540 | Kanjia | 40 | 40 | 100 | Har Gar Jal | Not Certified |
| 4 | Sitapur | Rampur Mathura | Jahanpur | 411541 | Nandanpur | 59 | 52 | 88 | Work In Progress | Not Certified |
| 5 | Sitapur | Rampur Mathura | Jahanpur | 411542 | Selhoamau | 108 | 90 | 83 | Work In Progress | Not Certified |