Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 8368566 | Chhee W/S Schemes | 332.62 | 138.69 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 25 | 25 | Yes | 0 | NA | No | 17455.00 | 17455.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Biswan | Bheera | 411107 | Bheera | 193 | 193 | 100 | Har Gar Jal | Certified |
| 2 | Sitapur | Biswan | Bisenda | 411115 | Bisenda | 740 | 740 | 100 | Har Gar Jal | Not Certified |
| 3 | Sitapur | Biswan | Chaharpur | 411120 | Chaharpur | 307 | 304 | 99 | Work In Progress | Not Certified |
| 4 | Sitapur | Biswan | Chhee | 411121 | Chhi | 506 | 494 | 98 | Work In Progress | Not Certified |
| 5 | Sitapur | Biswan | Hasanpur | 411128 | Hasnapur | 246 | 241 | 98 | Work In Progress | Not Certified |
| 6 | Sitapur | Biswan | Hathiya Gajipur | 411131 | Hanthia Gajipur | 482 | 475 | 99 | Work In Progress | Not Certified |