Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 8386658 | NANDAPAR G.P. WATER SUPPLY SCHEME | 389.01 | 301.06 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 33 | 33 | Yes | 0 | NA | No | 13146.00 | 12338.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Piprauli | Nandapar | 455160 | Nandapar | 349 | 316 | 91 | Work In Progress | Not Certified |
| 2 | Gorakhpur | Piprauli | Nandapar | 455161 | Chafkata | 96 | 96 | 100 | Har Gar Jal | Not Certified |
| 3 | Gorakhpur | Piprauli | Nandapar | 455162 | Kakana | 26 | 26 | 100 | Har Gar Jal | Not Certified |