Status Of NCs & Compliances

S.No.
District
TKC Total NCs reported Complainces Submitted By TKCs % Of Compliance Submitted No. of bills processed without compliances
(J)
Remarks(Only Critical in few words)
Critical
(A)
Major
(B)
Minor
(C )
Total
D = A+B+C
Critical
(E )
Major
(F)
Minor
(G)
Total
H=E+F+G
I = H*100/D
Total 53128 259652 15821 328601 44113 203337 12256 259706 79.03 11330
1 Varanasi
Larsen & Toubro Ltd 3554 25961 1245 30760 3204 22188 1055 26447 85.98 0 NA
2 Kushi Nagar
NCC Ltd. 2759 18926 252 21937 2736 18021 237 20994 95.70 621 1. A full-depth vertical crack has been developed in the boundary wall. 2.The hydro level transmitter is currently installed without a corresponding display or monitoring interface. Installation of the display unit is required to enable real-time level tracking and ensure operational visibility. 3.The solar panel has been found damaged and does not comply with electrical safety regulations, Damage
3 Prayagraj
Larsen & Toubro Ltd 2396 14424 501 17321 2217 13581 449 16247 93.80 0 IL road has been found settled and uneven surfaces.
VPRPL 318 997 19 1334 260 586 9 855 64.09 0 NA
GAJA - GAIPL JV 542 770 4 1316 508 702 4 1214 92.25 0 Admin Building Electrical wiring has been done without approved drawings.
4 Gorakhpur
NCC Ltd. 974 15136 810 16920 727 10822 549 12098 71.50 2627 1. Crack has been observed in the boundary wall. 6. Crack has been observed in the pump house floor. 7. Paint quality is not good of boundary wall. 8. Honeycomb has been observed in the OHT slab bottom. 9. Recharge pit chamber has been found damaged. 10. Honeycomb has been found in OHT TB-3. 11. Honeycomb has been observed in the OHT staircase Ramp. 12. Electromagnetic flow meter is not functionin
Rithwik-Koya (JV) 355 5536 278 6169 267 4472 157 4896 79.36 320 1. HDPE pipe found exposed condition end cap is not provided. 2.Boundary wall coping has been observed damage. 3. Lightning arrester has not been installed on the OHT. 4. The painting work on the OHT has not been done properly. 5. Crack has been found in the bpundary wall. 6. Water supply going on without chlorination.
5 Ghazipur
VSA 3305 6374 73 9752 1770 2130 17 3917 40.17 140 "1-Rusted steel used in ground beam work 2-Honeycombing is found in the Ring/Tie beam , Columns of the OHT. 3-Rusted bars are using in the construction of OHT foundation. 4-Cracks are found in the slab of the pump house. 5-Cracks are found in the boundary wall."
Larsen & Toubro Ltd 2961 5635 249 8845 2219 4057 215 6491 73.39 169 "1-The DPC layer of boundary wall is damaged 2- Honeycombing is found on the coping of the boundary wall 3- Honeycombing is found on the roof of the pump house."
HFCL- JWIL (JV) 1806 4166 100 6072 1601 3554 99 5254 86.53 0 "1-Width of the trench observed is 200mm at the top of the trench whereas as per DPR the width should be at least 600mm+ of pipe. 2-Quality of sand, 10mm, 20mm Aggregate not satisfactory 3- 75mm HDPE Pipe found laid in damage condition. 4-Depth of the trench is found 600mm at the top of the 63mm HDPE Pipe , whereas as per DPR the Depth should be at least 1000mm+ Dia of pipe. 5-MDPE pipe (20mm) f
6 Azamgarh
LC INFRA 1731 7125 330 9186 1720 5627 208 7555 82.24 0 "1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.) Construction materials such as cement, sand, aggregate, bricks and shuttering materials were not found of satisfactory quality and standards. 4) honeycomb was observed in major area of the raft foundation."
M/s Sudhakara Infratech Pvt. Ltd 1650 5276 125 7051 1282 3764 45 5091 72.20 0 "1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.)Rusted steel bars were used for slab and OHT work which Is not as per IS specificatons."
VIKRAN-VPRPL (JV) 403 1563 136 2102 340 652 41 1033 49.14 0 1.)Curing is not being done properly hence structure is not able to achieve its optimum strength.
GA INFRA - BABA (JV) 411 1487 53 1951 333 1207 17 1557 79.81 0 "1.) Backfilling of trenches after pipe laying is not being done layer-wise which could cause major accidents. 2.)The dia of the reinforcement bar was used 6 mm instead of 8mm in pump house slab beam. 3.)Material testing are not being done as per the norms due to which inadequate materials are used at site and could cause major failure of structure"
GAJA - SGIPL (JV) 227 1437 35 1699 175 1044 6 1225 72.10 0 "1.) The oversized gravel was used at site for raft foundation. 2.) The spacing of the Shear stirrups were not provided properly In column and Brace Beam."
SIEPL – BRCCPL (JV) / SKYLARK 225 755 103 1083 191 492 57 740 68.33 0  1.) proper layer wise compaction is not being performed which causes depression on road, resulting accidents
ECO PROTECTION ENGINEER 182 519 3 704 175 424 0 599 85.09 0 1.) The depth of the trench was found 700 mm at many locations whereas as per IS standard it should be 1 meter+dia of pipe.
7 Deoria
LC INFRA 1088 7928 71 9087 922 6473 56 7451 82.00 1948 1.-Cracks has been observed in wall of pump house.,2.Crack has been observed on the boundary wall.,3.Steel is visible in lintel beam of pump house.
Gayatri Projects LTD 989 7223 32 8244 913 6170 27 7110 86.24 1287 1.Crack has been observed on the boundary wall.,2.Steel is visible in coping of boundary wall.
Rithwik-Koya (JV) 203 2107 21 2331 161 1571 11 1743 74.77 101 1.3rd brace column finishing not done properly.,2.Honeycomb has been observed on the 6th lift staircase of OHT.
UNIVERSAL MEP 177 1160 8 1345 176 1065 7 1248 92.79 30 1.Crack has been observed on the boundary wall.2.Crack has been observed on coping of boundary wall.
8 Jaunpur
AFCONS 2793 5351 178 8322 2504 4922 150 7576 91.04 636 Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow
Welspun Kaveri Infraprojects JV 2032 5658 180 7870 1880 5108 164 7152 90.88 543 Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow and Road restoration work slow
9 Maharajganj
JMC - Kalpataru 667 7422 15 8104 603 6342 14 6959 85.87 486 1.Rusted steel found at construction site. 2.Honeycomb found in OHT 2nd brace beam. 3. Crack has been found in Boundary wall brick work below DPC. 4. Pump House apron has been settled down. 5. Crack observed in Boundary wall. 6.HDPE pipe found in damage condition. 7.Honey combing found in 2nd Brace beam.
Rithwik-Koya (JV) 419 3784 7 4210 321 2702 3 3026 71.88 0 1. Honeycombing found in OHT 2nd flight staircase landing. 2. Steel is visible in OHT stair case cantilever beam. 3.OHT 1st lift column has been broken and extra reinforcement is not available for further casting. 4.Pump house Apron found damaged. 5. Steel is visible in OHT 1st brace beam above lift column. 6. Crack found on the wall of Pump house.
10 Fatehpur
Gayatri Projects LTD 354 7052 311 7717 219 3092 95 3406 44.14 0 NA
Power Mech Projects Ltd 885 5780 246 6911 674 3776 149 4599 66.55 0 "1.One panel of boundary wall has been found collapsed due to soil stacked behind it. 2.boundary wall has been found collapsed. The length was aprox. 15 mtr."
GA INFRA - BABA (JV) 173 1059 42 1274 125 612 14 751 58.95 0 "1.Pea gravel packing in chamber of Pump House has not been done. 2.Tube Well has been left without bore well cap which may cause menace in village."
11 Chandauli
VSA 1029 6330 255 7614 1018 6197 251 7466 98.06 0 "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weigh
ION EXCHANGE 675 6166 78 6919 635 5638 71 6344 91.69 0 "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weigh
GA INFRA - BABA (JV) 258 3514 78 3850 252 3366 72 3690 95.84 0 "1-Hand concrete mixer is being used for concrete mixing instead of weightbatch concrete mixer. 2-Dirty water used for mixing of concreting, which is against clause 4.6 of IS;2250 3-Honeycomb observed in Pump house ( Chajja) 4-Rusted reinforcement use in pump house slab 5-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new brick for re
HFCL- JWIL (JV) 168 1523 23 1714 159 1358 21 1538 89.73 0 "1-Hand concrete mixer used for concrete mixing Instead of PLC based weighbatch concrete mixer. 2-Depth found 800mm found for 63mm Dia HDPE Pipe laying as per DPR it should be 1000mm+Dia 3-Second class bricks are available at site, whereas per the DPR 1st class bricks should be used. 4-Curing of concrete of boundary wall coping casting work not done after de-shuttering. 5-MDPE pipe found above the
East India Udhyog- Kaveri JV 17 451 1 469 16 353 1 370 78.89 0 Road Restoration work is pending at site .
12 Mau
LC INFRA 742 5548 10 6300 621 2830 10 3461 54.94 0 "1.) Severe cracks were observed in the boundary wall due to lack of curing work 2.)Multiple lapping is provided at a single section of the beam/raft which could reduce the strength of structure at those locations."
GA INFRA-VPL 439 5118 17 5574 263 2931 17 3211 57.61 0 "1.)End cap found open due to which insects are entering through the inlet of the pipe, it may cause various diseases in supplied water. 2.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents."
KLSR - RAYS (JV) 76 2322 16 2414 56 816 16 888 36.79 0 "1.) Open trench was found, after laying HDPE pipe soil back filling was not done it's more than 3days; which may cause accidents. 2.) Dent was found over the screen pipe which may leads to collapse of assembly system."
13 Kaushambi
GA INFRA - BABA (JV) 761 4600 317 5678 452 2698 217 3367 59.30 0 No cut out has been made at the slab of the oht for inlet and outlet pipe. As hammering in slab should be avoided to counter strength reduction.
JMC - Kalpataru 630 3692 225 4547 599 3323 205 4127 90.76 0 Honeycomb has been observed at the outer face of conical wall . poor work was done for the construction of conical wall.
14 Pratapgarh
JMC - Kalpataru 977 4234 217 5428 923 3769 193 4885 90.00 0 Painting is frayed out due to dampness, Crack has been started developing in the boundary wall.
Power Mech Projects Ltd 1521 3650 68 5239 1463 2914 32 4409 84.16 0 panels of the boundary wall have been found collapsed, Steel bars of OHT columns have been cut at a section instead of staggered manner. And also steel bars are rusted due to work sttoped.
15 Mirzapur
GA INFRA 1055 3564 125 4744 1044 3259 125 4428 93.34 28 1 - Wall of staff quater found damaged., 2 - S.valve found damaged 3 -Plinth protection of staff quater found damaged. 4 -·Boundary wall found damaged..
NCC Ltd. 393 3153 270 3816 374 3127 270 3771 98.82 73 1 - Depth of HDPE Pipe is 750 MM., 2 -·Crack has been observed in ladder of MBR., 3 - Water logging in ESR campus, 4-Boundary wall collapsed, 5 -Leakage has been found due to not proper pipe fittings
Megha 722 2867 81 3670 448 2118 72 2638 71.88 31 1 - Many Leakage/seepage points have been observed in the CWR tank. , 2 - Water has accumulated near the ESR structure , 3 - Water logging on the chamber floor – Stagnant water was found inside the pump house, which poses a risk of electrical hazards and may cause damage to equipment.
Ramky baba 423 2154 153 2730 38 213 25 276 10.11 20 1 - Significant water stagnation observed around the rcc pedestal of the OHT 2 - The adjacent soil appears soft ,damp,and partialy eroded. 3- Signs of algae formation and water logging persist despite multiple site visits
GVPR 172 1472 49 1693 67 560 26 653 38.57 68 1 - Leakage/seepage found in ESR bottom dome. 2 -The level of the stairs does not seem to be correct, the stairs appear to be tilted to one side.
Multiurban 50 267 10 327 50 263 10 323 98.78 4        The Overhead Tank (OHT) campus has not been properly developed, with visible neglect in landscaping and basic infrastructure.
16 Sant Ravidas Nagar
Welspun Kaveri Infraprojects JV 1166 3201 337 4704 985 2644 195 3824 81.29 1086 1. Washer and lock nut not provided in solar foundation. 2. Crack has been found in pump house wall. 3. Staircase thread & riser size is not found ok. 4. Staircase 1st landing slab size & level not found properly. 5. ESR work has been stopped for almost 5 months. 6. There is a lot of rust in the reinforcement used in ESR, due to which the upper layer of the steel is slowly getting destroyed.
GA INFRA - BABA (JV) 1032 2336 205 3573 1022 2284 201 3507 98.15 740 1. The cement placed in rampur ESR location has completely set. 2. The soil of the foundation of the boundary wall of Rampur ESR has been washed away by rain, due to which the boundary wall can collapse any time. 3. Crack has been found in boundary wall at many places. 4. Boundary wall plumb & alignment is not found properly. 5. Honeycombing has been found in ESR column and beam at many places. 6
17 Hardoi
NCC Ltd. 1329 1616 1313 4258 996 1279 1165 3440 80.79 0 1)Major cracks seen on boundary wall. 2)Pea gravel not stacked properly at site. 3)FHTC installed outside the house. 3) Disinfection of pipe not done 4) Lifting appliances, lifting gears and Compressor was not inspected by competent agency 5) Test certificate scaffolding material not submitted.6) Nonstandard scaffolding used at site.7) Non-standard DG used at site.7) Quality issues during OHT work
18 Sonbhadra
VPRPL 165 2746 98 3009 165 2284 68 2517 83.65 39 1 - After completion of pipe laying work BT road dismantled but it has not been restored. 2- After completion of pipe laying work BT road dismantled but it has not been restored.
NCC Ltd. 109 2328 28 2465 109 1816 20 1945 78.90 214 1.Waste slab thickness not found as per drawing specifications. 2. Rise and trade not found as per drawing specifications.
Larsen & Toubro Ltd 47 1817 62 1926 47 1455 43 1545 80.22 66 1. Pipe joint is leakage from more than 4 months. 2. Flange is welded with pipe which is not acceptable at any cost.
GVPR 119 1260 40 1419 119 1054 23 1196 84.28 0
Jain Const. 9 176 14 199 9 176 14 199 100.00 18 No Critical NC This Week.
19 Lucknow
NCC Ltd. 202 1679 553 2434 88 820 553 1461 60.02 0
20 Ballia
GAJA - GAIPL JV 245 1632 6 1883 216 1251 0 1467 77.91 0 1. Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor. 2. Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor.
Larsen & Toubro Ltd 428 1242 10 1680 426 1146 8 1580 94.05 0 1. Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor.
Eagle Infra- Sudhakara Infra JV 265 857 10 1132 255 601 8 864 76.33 0 1 Proper finishing not found of OHT Stair .Curing not properly done 2. Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor.
21 Lakhimpur Kheri
NCC Ltd. 393 733 121 1247 129 532 90 751 60.22 0 1- Grouting work not completed in ZnAl tank, 2- Major honeycombing observed in OHT.
Vindhya-GAJA (JV) 201 379 91 671 71 221 61 353 52.61 0 1- Honeycombing found in OHT column & brace beam, 2- Poor quality of workmanship in oht work.
22 Lalitpur
M/s Sudhakara Infratech Pvt. Ltd 67 55 829 951 67 55 741 863 90.75 0
JMC-JWIL (JV) 48 66 413 527 48 66 344 458 86.91 0
DARA ENGINEERING 45 79 348 472 45 79 302 426 90.25 0
Banko Ganga 5 10 85 100 5 10 74 89 89.00 0
Brija Banco Pvt. Ltd 10 18 52 80 10 18 31 59 73.75 0
23 Raebareli
NCC Ltd. 47 428 78 553 44 428 78 550 99.46 0 Honey combing found in OHT, Leakage observed in OHT
Vindhya-GAJA (JV) 36 211 20 267 26 195 20 241 90.26 0 Poor quality of workmanship in OHT work, Leakage found in pipeline, Honey combing found in OHT.
24 Basti
Megha 126 189 189 504 105 124 148 377 74.80 0
JAKSON - VISHVARAJ (JV) 11 35 24 70 9 32 24 65 92.86 0
VSA 6 13 19 38 6 11 15 32 84.21 0
25 Jhansi
BGCCPL-Ramky (JV) 29 140 303 472 29 102 196 327 69.28 0
NCC Ltd. 26 93 295 414 26 93 269 388 93.72 0
Indian Hume Pipe 16 40 65 121 16 40 56 112 92.56 0
DARA ENGINEERING 19 31 62 112 19 31 58 108 96.43 0
Unipro 20 28 50 98 20 28 48 96 97.96 0
26 Saharanpur
GA INFRA - BABA (JV) 88 251 17 356 67 140 16 223 62.64 0 Poor Quality work OHT 3rd brace beam & column not plumb. Without complete staircase work & plumb of brace beam Inappropriate size of staircase Poor Quality work OHT column found honeycomb
NKG-PRIMUS (JV) 9 118 6 133 6 71 4 81 60.90 0 Poor quality construction work pump house. CC road reinstatement poor workmanship.
Gayatri Projects LTD 10 120 2 132 7 31 0 38 28.79 0 Poor quality construction work pump house. CC road reinstatement poor workmanship.
27 Sultanpur
Vindhya-GAJA (JV) 82 128 134 344 65 60 74 199 57.85 0
Gayatri Projects LTD 19 19 18 56 14 10 14 38 67.86 0
UNIVERSAL MEP 13 11 13 37 13 11 13 37 100.00 0
28 Kasganj
PNC-SPML-JV 36 242 65 343 35 226 64 325 94.75 0
ION EXCHANGE 0 1 0 1 0 0 0 0 0.00 0
29 Sitapur
NCC Ltd. 317 0 0 317 18 0 0 18 5.68 0
Larsen & Toubro Ltd 0 46 110 156 0 24 60 84 53.85 0
30 Hathras
BGCCPL-Ramky (JV) 43 84 184 311 31 60 152 243 78.14 0
ION EXCHANGE 11 21 14 46 10 19 14 43 93.48 0 Work done without RFI & Reinstatement work not as per standard specification
31 Agra
Megha 201 62 16 279 108 31 8 147 52.69 0
NCC-APCO JV 67 33 11 111 54 29 11 94 84.68 0
32 Muzaffarnagar
JMC - Kalpataru 149 108 14 271 123 54 8 185 68.27 0 -
NKG-PRIMUS (JV) 62 26 3 91 25 1 0 26 28.57 0 -
Gayatri Projects LTD 2 4 0 6 2 4 0 6 100.00 0 -
33 Firozabad
Larsen & Toubro Ltd 5 253 7 265 5 199 7 211 79.62 0
NCC Ltd. 0 156 1 157 0 153 1 154 98.09 0
34 Moradabad
NKG-PRIMUS (JV) 33 101 122 256 32 20 22 74 28.91 0
LC INFRA 40 20 169 229 40 18 35 93 40.61 0
35 Amroha
OMIL-JWIL (JV) 90 121 44 255 80 117 41 238 93.33 0 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT 6) Zinc alum tank leakage
PNC SPML- JV Moradabad 85 91 36 212 61 84 31 176 83.02 0 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT
LC INFRA 3 2 3 8 2 2 3 7 87.50 0 1)Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT
36 Siddharth Nagar
Megha 59 174 17 250 51 157 5 213 85.20 0
JAKSON - VISHVARAJ (JV) 55 14 69 138 45 12 57 114 82.61 0
VSA 29 85 7 121 23 85 1 109 90.08 0
37 Budaun
PNC-SPML-JV 75 149 8 232 75 149 8 232 100.00 0
NCC Ltd. 3 4 2 9 3 4 2 9 100.00 0
38 Jalaun
BGCCPL-Ramky (JV) 118 80 32 230 47 27 12 86 37.39 17 Revised drawings are still awaited for approval. Approved drawings are often not available at site of work.
GVPR 40 40 16 96 29 26 12 67 69.79 18 Revised drawings are still awaited for approval. Approved drawings are often not available at site of work.
39 Kannauj
VSA 43 78 79 200 40 75 70 185 92.50 0 ZN-AL tank Fusion Not Done, Road Restoration Not Done, Column misalignment observed, honeycomb observed, work Without RFI
GVPR 19 59 40 118 18 56 32 106 89.83 0 Road Restoration Not Done, honeycomb observed, work Without RFI
40 Ambedkar Nagar
Vindhya-GAJA (JV) 56 133 3 192 56 88 2 146 76.04 0
Welspun Kaveri Infraprojects JV 11 30 2 43 11 17 2 30 69.77 0
41 Sant Kabeer Nagar
Megha 35 95 55 185 22 23 22 67 36.22 0 1. The precast OHT slab is not level. 2. Step height of precast stair structure is not according to drawing.
JAKSON - VISHVARAJ (JV) 22 74 61 157 20 23 13 56 35.67 0 Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing. Alignment of beam is not as per drawing and design.
VISHVARAJ 24 50 24 98 20 24 8 52 53.06 0 OHt staircase railing is not properly installed.
JAKSON 8 36 43 87 6 3 5 14 16.09 0 "Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing."
42 Kanpur Nagar
Vindhya-GAJA (JV) 84 35 52 171 73 35 52 160 93.57 0
VSA 33 21 34 88 28 21 34 83 94.32 0
43 Bareilly
NCC Ltd. 67 60 36 163 41 59 36 136 83.44 0 Verticality & UPV results not satisfactory
44 Aligarh
PNC-SPML-JV 16 120 9 145 16 115 9 140 96.55 0
JMC - Kalpataru 13 88 2 103 13 87 2 102 99.03 0
ION EXCHANGE 12 52 14 78 12 49 14 75 96.15 0
45 Bahraich
PNC-SPML-JV 44 76 18 138 44 70 16 130 94.20 0 1. Piling work is being done without approval of Methodology . 2. As build drawing not submitted to UPJN and TPI also
GA INFRA-VPL 9 14 8 31 5 12 8 25 80.65 0 HDD Method is not implementing in possible site locations 2. Lack of proper road restoration works. 3. Lack of manpower, physical work progress is very slow. 4. As build drawing not submitted to UPJN office and to TPI also.
46 Shamli
JMC - Kalpataru 54 70 9 133 35 12 6 53 39.85 0
JMC - Lakshmi (JV) 54 70 9 133 35 13 6 54 40.60 0
Gayatri Projects LTD 2 4 2 8 2 0 0 2 25.00 0
47 Barabanki
Megha 75 54 2 131 39 17 1 57 43.51 0
PNC-SPML-JV 53 50 2 105 43 25 1 69 65.71 0
Vindhya-GAJA (JV) 28 22 0 50 22 16 0 38 76.00 0
VSA 12 13 0 25 12 6 0 18 72.00 0
Gayatri Projects LTD 5 9 0 14 4 1 0 5 35.71 0
48 Farrukhabad
GVPR 33 54 39 126 21 39 21 81 64.29 0
Vindhya-GAJA (JV) 2 35 21 58 2 31 21 54 93.10 0
49 Mainpuri
NCC Ltd. 33 71 19 123 27 57 18 102 82.93 0
50 Gonda
KLSR - RAYS (JV) 54 40 27 121 35 18 13 66 54.55 0 Misalignment, Major Honeycomb, Road Restoration, Cube Test Fail and water supply without Chlorination. Cracks in Plinth protection and BW.
Larsen & Toubro Ltd 2 48 17 67 2 39 9 50 74.63 0 Road Restoration and water supply without chlorination.
51 Pilibhit
PNC-SPML-JV 27 30 60 117 27 30 60 117 100.00 0 all compliances have been submitted by the firm.
VISHVARAJ 11 16 49 76 11 16 49 76 100.00 0
52 Ayodhya
VSA 40 45 22 107 34 20 10 64 59.81 0
UNIVERSAL MEP 2 25 10 37 2 25 9 36 97.30 0
Vindhya-GAJA (JV) 8 15 7 30 7 12 5 24 80.00 0
Gayatri Projects LTD 5 14 4 23 5 13 4 22 95.65 0
53 Auraiya
GVPR 69 29 6 104 69 29 6 104 100.00 0
Indian Hume Pipe 9 14 3 26 9 14 3 26 100.00 0
54 Hamirpur
JWIL 5 4 86 95 5 4 86 95 100.00 0
PNC-SPML-JV 6 4 68 78 6 4 68 78 100.00 0
55 Etawah
Indian Hume Pipe 24 42 20 86 24 42 20 86 100.00 0
OMIL-JWIL (JV) 39 17 4 60 28 17 4 49 81.67 0
56 Banda
Larsen & Toubro Ltd 9 9 67 85 9 9 67 85 100.00 0
NCC Ltd. 9 11 29 49 9 11 29 49 100.00 0
57 Sambhal
PNC SPML- JV Moradabad 20 30 35 85 18 25 30 73 85.88 0
NKG-PRIMUS (JV) 15 30 38 83 14 25 30 69 83.13 0
LC INFRA 0 0 0 0 0 0 0 0 0.00 0
58 Amethi
Vindhya-GAJA (JV) 19 33 30 82 19 21 14 54 65.85 0
Gayatri Projects LTD 14 24 28 66 14 13 12 39 59.09 0
Welspun Kaveri Infraprojects JV 12 13 20 45 11 10 16 37 82.22 0
59 Kanpur Dehat
VSA 34 21 23 78 27 18 23 68 87.18 0 Honey comb and cube fail
GVPR 4 9 10 23 4 9 10 23 100.00 0 Major Honeycomb
Indian Hume Pipe 6 5 10 21 5 5 10 20 95.24 0 Cube fail and honey comb
Vindhya-GAJA (JV) 2 5 2 9 2 5 2 9 100.00 0 Zn Al
60 Balrampur
Larsen & Toubro Ltd 13 30 32 75 10 27 30 67 89.33 0 Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. 2) Pump house finishing work is not proper. 3) Lot of road restoration work is pending from the agency and quality of road restoration is not as per standard. 4. As build drawing not submitted to UPJN and TPI.
Dara- Eco Protection (JV) 14 25 22 61 11 22 21 54 88.52 0 Plywood doors have been installed in 17 Gram Panchayats. 2) HDD Method is not implementing in possible site locations. 3. Hydrotesting, disinfection, and flushing of the pipeline not done before water supply. 4. As build drawing not submitted to UPJN and TPI.
61 Shahjahanpur
NCC Ltd. 18 29 25 72 18 27 22 67 93.06 0
62 Mahoba
JMC-JWIL (JV) 13 27 24 64 13 27 24 64 100.00 0
SLC-SMC (JV) 7 16 12 35 7 15 12 34 97.14 0
Larsen & Toubro Ltd 6 14 12 32 6 14 12 32 100.00 0
N.K. Gupta & K.B. Gupta Contractors 6 10 8 24 6 10 8 24 100.00 0
63 Bulandshahr
JMC - Kalpataru 1 59 3 63 1 59 2 62 98.41 0
Welspun Kaveri Infraprojects JV 0 28 0 28 0 24 0 24 85.71 0
Power Mech Projects Ltd 2 10 1 13 2 10 1 13 100.00 0
64 Rampur
OMIL-JWIL (JV) 19 27 3 49 15 19 2 36 73.47 0 RFI was not raised. 2.Quality of material not as per specification.3. Safety norms not followed, approved drawing not at site.
NKG-PRIMUS (JV) 12 22 6 40 9 13 0 22 55.00 0 OHT construction, cube testing failure, CC road restoration done work without raised RFI, OHT column beam misalignment, staircase not as per drawing
LC INFRA 1 4 0 5 1 2 0 3 60.00 0 Brick Quality is not good 2.Poor workmanship3.Caution Tape not used 4. Safety belt not used during OHT heighted work 5.PPE kit not used.
PNC SPML- JV Moradabad 0 0 0 0 0 0 0 0 0.00 0
65 Bijnor
Vindhya-GAJA (JV) 23 6 19 48 22 4 15 41 85.42 0 un approved steel and cement,column alignment not in plumb,major honeycombs.
LC INFRA 7 3 4 14 7 2 4 13 92.86 0 column alignment not in plumb,major honeycombs,brace beam shuttering found bulge.
66 Chitrakoot
Larsen & Toubro Ltd 9 16 20 45 9 16 18 43 95.56 0
GVPR 5 6 21 32 5 3 16 24 75.00 0
67 Shravasti
Larsen & Toubro Ltd 13 18 13 44 11 15 13 39 88.64 0 1) Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. Many schemes HDPE Pipe distribution line is found open without providing end caps. 2. Site Order Book , Approved drawings are not available at site premise during execution. 3. As build drawing not submitted to UPJN and TPI.
GA INFRA-VPL 0 33 0 33 0 12 0 12 36.36 0 Cube fail -2 / Honeycomb -3 / Water logged -1 / Steel cut upto GL -1 / Steel rusted -5
68 Ghaziabad
LC INFRA 6 15 10 31 5 11 3 19 61.29 0
69 Hapur
LC INFRA 4 4 19 27 4 4 19 27 100.00 0
70 Gautam Buddha Nagar
LC INFRA 2 2 13 17 2 2 13 17 100.00 0
71 Etah
Power Mech Projects Ltd 0 0 10 10 0 0 10 10 100.00 0
JMC - Kalpataru 0 0 6 6 0 0 6 6 100.00 0
ION EXCHANGE 0 4 0 4 0 3 0 3 75.00 0
72 Meerut
Power Mech Projects Ltd 2 0 0 2 2 0 0 2 100.00 0
73 Mathura
NCC-APCO JV 1 0 0 1 0 0 0 0 0.00 0
74 Baghpat
LC INFRA 0 0 0 0 0 0 0 0 0.00 0