| S.No. |
District
|
TKC | Total NCs reported | Complainces Submitted By TKCs | % Of Compliance Submitted | No. of bills processed without compliances (J) |
Remarks(Only Critical in few words) |
||||||
| Critical (A) |
Major (B) |
Minor (C ) |
Total D = A+B+C |
Critical (E ) |
Major (F) |
Minor (G) |
Total H=E+F+G |
I = H*100/D | |||||
| Total | 52629 | 247828 | 15526 | 315983 | 42878 | 194953 | 12251 | 250082 | 79.14 | 8664 | |||
| 1 |
Varanasi |
Larsen & Toubro Ltd | 3542 | 25724 | 1224 | 30490 | 3204 | 22188 | 1055 | 26447 | 86.74 | 0 | 1-Cracks observed in Boundary wall. 2-Road Restoration work was not done properly at some places. 3-Joints of brickwork are not filled properly 4-Mortar used for the Brick work was not as per DPR and specifications. |
| 2 |
Kushi Nagar |
NCC Ltd. | 2722 | 17556 | 229 | 20507 | 2716 | 17424 | 210 | 20350 | 99.23 | 621 | 1. A full-depth vertical crack has been developed in the boundary wall. 2.The hydro level transmitter is currently installed without a corresponding display or monitoring interface. Installation of the display unit is required to enable real-time level tracking and ensure operational visibility. 3.The solar panel has been found damaged and does not comply with electrical safety regulations, Damage |
| 3 |
Prayagraj |
Larsen & Toubro Ltd | 2393 | 13971 | 481 | 16845 | 2246 | 13498 | 448 | 16192 | 96.12 | 0 | Leakage has been found from the Liner of the OHTs |
| GAJA - GAIPL JV | 516 | 695 | 3 | 1214 | 492 | 626 | 3 | 1121 | 92.34 | 0 | Misalignment has found in the column of the OHT | ||
| VPRPL | 313 | 746 | 14 | 1073 | 271 | 564 | 8 | 843 | 78.56 | 0 | Seepage has been found from the OHT | ||
| 4 |
Gorakhpur |
NCC Ltd. | 956 | 14643 | 663 | 16262 | 714 | 10460 | 498 | 11672 | 71.77 | 2627 | 1. Crack has been observed in the boundary wall. 6. Crack has been observed in the pump house floor. 7. Paint quality is not good of boundary wall. 8. Campus approach road has been settled down. 9. Recharge pit chamber has been found damaged. 10. Honeycomb has been found in OHT TB-2. |
| Rithwik-Koya (JV) | 347 | 5336 | 217 | 5900 | 262 | 4464 | 145 | 4871 | 82.56 | 320 | 1. HDPE pipe found exposed condition end cap is not provided. 2.Boundary wall coping has been observed damage. 3. Lightning arrester has not been installed on the OHT. 4. The painting work on the OHT has not been done properly. 5. Crack has been found in the bpundary wall. | ||
| 5 |
Ghazipur |
VSA | 3305 | 6374 | 73 | 9752 | 1770 | 2130 | 17 | 3917 | 40.17 | 140 | "1-Rusted steel used in ground beam work 2-Honeycombing is found in the Ring/Tie beam , Columns of the OHT. 3-Rusted bars are using in the construction of OHT foundation. 4-Cracks are found in the slab of the pump house. 5-Cracks are found in the boundary wall." |
| Larsen & Toubro Ltd | 2961 | 5635 | 249 | 8845 | 2219 | 4057 | 215 | 6491 | 73.39 | 169 | "1-The DPC layer of boundary wall is damaged 2- Honeycombing is found on the coping of the boundary wall 3- Honeycombing is found on the roof of the pump house." | ||
| HFCL- JWIL (JV) | 1806 | 4166 | 100 | 6072 | 1601 | 3554 | 99 | 5254 | 86.53 | 0 | "1-Width of the trench observed is 200mm at the top of the trench whereas as per DPR the width should be at least 600mm+ of pipe. 2-Quality of sand, 10mm, 20mm Aggregate not satisfactory 3- 75mm HDPE Pipe found laid in damage condition. 4-Depth of the trench is found 600mm at the top of the 63mm HDPE Pipe , whereas as per DPR the Depth should be at least 1000mm+ Dia of pipe. 5-MDPE pipe (20mm) f | ||
| 6 |
Deoria |
LC INFRA | 1081 | 7752 | 69 | 8902 | 831 | 5674 | 50 | 6555 | 73.64 | 1948 | 1.-Cracks has been observed in wall of pump house.,2.Crack has been observed on the boundary wall.,3.Steel is visible in lintel beam of pump house. |
| Gayatri Projects LTD | 986 | 6999 | 32 | 8017 | 985 | 6023 | 25 | 7033 | 87.73 | 1287 | 1.Crack has been observed on the boundary wall.,2.Steel is visible in coping of boundary wall. | ||
| Rithwik-Koya (JV) | 201 | 2040 | 21 | 2262 | 159 | 1515 | 11 | 1685 | 74.49 | 101 | 1.3rd brace column finishing not done properly.,2.Honeycomb has been observed on the 6th lift staircase of OHT. | ||
| UNIVERSAL MEP | 177 | 1045 | 8 | 1230 | 175 | 998 | 7 | 1180 | 95.93 | 30 | 1.Crack has been observed on the boundary wall.2.Crack has been observed on coping of boundary wall. | ||
| 7 |
Jaunpur |
AFCONS | 2793 | 5351 | 178 | 8322 | 2504 | 4922 | 150 | 7576 | 91.04 | 636 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow |
| Welspun Kaveri Infraprojects JV | 2032 | 5658 | 180 | 7870 | 1880 | 5108 | 164 | 7152 | 90.88 | 543 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow and Road restoration work slow | ||
| 8 |
Azamgarh |
LC INFRA | 1725 | 6158 | 276 | 8159 | 1608 | 4978 | 192 | 6778 | 83.07 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.) Construction materials such as cement, sand, aggregate, bricks and shuttering materials were not found of satisfactory quality and standards. 3) honeycomb was observed in major area of the raft foundation. |
| M/s Sudhakara Infratech Pvt. Ltd | 1635 | 4658 | 115 | 6408 | 1175 | 3239 | 41 | 4455 | 69.52 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.)Rusted steel bars were used for slab and OHT work which Is not as per IS specification's. | ||
| GA INFRA - BABA (JV) | 409 | 1354 | 53 | 1816 | 141 | 464 | 13 | 618 | 34.03 | 0 | 1.) Backfilling of trenches after pipe laying is not being done layer-wise which could cause major accidents. 2.)The dia of the reinforcement bar was used 6 mm instead of 8mm in pump house slab beam. 3.)Material testing are not being done as per the norms due to which inadequate materials are used at site and could cause major failure of structure. | ||
| VIKRAN-VPRPL (JV) | 380 | 863 | 120 | 1363 | 288 | 412 | 35 | 735 | 53.93 | 0 | Curing is not being done properly hence structure is not able to achieve its optimum strength. | ||
| GAJA - SGIPL (JV) | 221 | 1098 | 23 | 1342 | 140 | 790 | 5 | 935 | 69.67 | 0 | 1.) The oversized gravel was used at site for raft foundation. 2.) The spacing of the Shear stirrups were not provided properly In column and Brace Beam. | ||
| SIEPL – BRCCPL (JV) / SKYLARK | 221 | 527 | 84 | 832 | 93 | 228 | 15 | 336 | 40.38 | 0 | Proper layer wise compaction is not being performed which causes depression on road, resulting accidents | ||
| ECO PROTECTION ENGINEER | 181 | 396 | 3 | 580 | 166 | 374 | 0 | 540 | 93.10 | 0 | The depth of the trench was found 700 mm at many locations whereas as per IS standard it should be 1 meter+dia of pipe. | ||
| 9 |
Maharajganj |
JMC - Lakshmi (JV) | 660 | 7251 | 15 | 7926 | 580 | 6195 | 14 | 6789 | 85.65 | 0 | Leakage has been found in OHT Bottom Dome. Honeycombing found in OHT 3rd flight staircase Cantilever beam. |
| Rithwik-Koya (JV) | 419 | 3626 | 7 | 4052 | 302 | 2571 | 3 | 2876 | 70.98 | 0 | The zinc OHT liner is popping out under the sheet near the balcony. Additional reinforcement not available for further casting of the OHT column. | ||
| 10 |
Chandauli |
VSA | 1029 | 6330 | 255 | 7614 | 1018 | 6197 | 251 | 7466 | 98.06 | 0 | "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weigh |
| ION EXCHANGE | 675 | 6166 | 78 | 6919 | 635 | 5638 | 71 | 6344 | 91.69 | 0 | "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weigh | ||
| GA INFRA - BABA (JV) | 258 | 3514 | 78 | 3850 | 252 | 3366 | 72 | 3690 | 95.84 | 0 | "1-Hand concrete mixer is being used for concrete mixing instead of weightbatch concrete mixer. 2-Dirty water used for mixing of concreting, which is against clause 4.6 of IS;2250 3-Honeycomb observed in Pump house ( Chajja) 4-Rusted reinforcement use in pump house slab 5-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new brick for re | ||
| HFCL- JWIL (JV) | 168 | 1523 | 23 | 1714 | 159 | 1358 | 21 | 1538 | 89.73 | 0 | "1-Hand concrete mixer used for concrete mixing Instead of PLC based weighbatch concrete mixer. 2-Depth found 800mm found for 63mm Dia HDPE Pipe laying as per DPR it should be 1000mm+Dia 3-Second class bricks are available at site, whereas per the DPR 1st class bricks should be used. 4-Curing of concrete of boundary wall coping casting work not done after de-shuttering. 5-MDPE pipe found above the | ||
| East India Udhyog- Kaveri JV | 17 | 451 | 1 | 469 | 16 | 353 | 1 | 370 | 78.89 | 0 | Road Restoration work is pending at site . | ||
| 11 |
Fatehpur |
Gayatri Projects LTD | 342 | 6943 | 303 | 7588 | 162 | 2696 | 80 | 2938 | 38.72 | 0 | The earthing work of pump plant has not been done. |
| Power Mech Projects Ltd | 854 | 5549 | 216 | 6619 | 540 | 3198 | 115 | 3853 | 58.21 | 0 | Hard barricading and sign boards have not been used at site. | ||
| GA INFRA - BABA (JV) | 162 | 1017 | 35 | 1214 | 106 | 487 | 4 | 597 | 49.18 | 0 | Poor lighting arrangement has been found in the storage area. | ||
| 12 |
Mau |
LC INFRA | 738 | 5179 | 149 | 6066 | 595 | 2345 | 108 | 3048 | 50.25 | 0 | 1.) Severe cracks were observed in the boundary wall due to lack of curing work 2.)Multiple lapping is provided at a single section of the beam/raft which could reduce the strength of structure at those locations. |
| GA INFRA-VPL | 429 | 4328 | 17 | 4774 | 221 | 2384 | 14 | 2619 | 54.86 | 0 | 1.)End cap found open due to which insects are entering through the inlet of the pipe, it may cause various diseases in supplied water. 2.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents. | ||
| KLSR - RAYS (JV) | 75 | 1792 | 16 | 1883 | 56 | 690 | 2 | 748 | 39.72 | 0 | 1.) Open trench was found, after laying HDPE pipe soil back filling was not done it's more than 3days; which may cause accidents. 2.) Dent was found over the screen pipe which may leads to collapse of assembly system. | ||
| 13 |
Kaushambi |
GA INFRA - BABA (JV) | 742 | 4433 | 302 | 5477 | 392 | 2459 | 204 | 3055 | 55.78 | 0 | No cut out has been made at the slab of the oht for inlet and outlet pipe. As hammering in slab should be avoided to counter strength reduction. |
| JMC - Lakshmi (JV) | 616 | 3472 | 209 | 4297 | 518 | 2924 | 175 | 3617 | 84.18 | 0 | Honeycomb has been observed at the outer face of conical wall . Conical wall of the ESR has poorly constructed. | ||
| 14 |
Pratapgarh |
JMC - Lakshmi (JV) | 943 | 4118 | 206 | 5267 | 912 | 3753 | 193 | 4858 | 92.23 | 0 | The riser of 1st flight stair is found 200 mm at site while it should be 165mm as per drawing. Cracks have been started developing at several places in the boundary wall. |
| Power Mech Projects Ltd | 1475 | 3554 | 62 | 5091 | 1460 | 2914 | 32 | 4406 | 86.54 | 0 | Mud has been accumulated inside the water recharge chamber. The bore cap has not been fitted in the tube well, due to which bricks and stones have fallen into it, which is very difficult to remove and the bore well may collapse. The bore cap has not been fitted in the tube well, due to which bricks and stones have fallen into it, which is very difficult to remove and the bore well may collapse. | ||
| 15 |
Mirzapur |
GA INFRA | 1044 | 3250 | 125 | 4419 | 1044 | 3250 | 125 | 4419 | 100.00 | 25 | 1 - Wall of staff quater found damaged., 2 - S.valve found damaged 3 -Plinth protection of staff quater found damaged. 4 -·Boundary wall found damaged.. |
| NCC Ltd. | 390 | 3127 | 270 | 3787 | 374 | 3127 | 270 | 3771 | 99.58 | 62 | 1 - Depth of HDPE Pipe is 750 MM., 2 -·Crack has been observed in ladder of MBR., 3 - Water logging in ESR campus, 4-Boundary wall collapsed, 5 -Leakage has been found due to not proper pipe fittings | ||
| Megha | 721 | 2745 | 81 | 3547 | 448 | 2118 | 72 | 2638 | 74.37 | 49 | 1 - Many Leakage/seepage points have been observed in the CWR tank. , 2 - Water has accumulated near the ESR structure , 3 - Water logging on the chamber floor – Stagnant water was found inside the pump house, which poses a risk of electrical hazards and may cause damage to equipment. | ||
| Ramky baba | 423 | 2077 | 153 | 2653 | 38 | 213 | 25 | 276 | 10.40 | 32 | 1 - Significant water stagnation observed around the rcc pedestal of the OHT 2 - The adjacent soil appears soft ,damp,and partialy eroded. 3- Signs of algae formation and water logging persist despite multiple site visits | ||
| GVPR | 172 | 1397 | 49 | 1618 | 67 | 560 | 26 | 653 | 40.36 | 20 | 1 - Leakage/seepage found in ESR bottom dome. 2 -The level of the stairs does not seem to be correct, the stairs appear to be tilted to one side. | ||
| Multiurban | 50 | 263 | 10 | 323 | 50 | 263 | 10 | 323 | 100.00 | 19 | The Overhead Tank (OHT) campus has not been properly developed, with visible neglect in landscaping and basic infrastructure. | ||
| 16 |
Sant Ravidas Nagar |
Welspun Kaveri Infraprojects JV | 1150 | 2933 | 267 | 4350 | 980 | 2573 | 175 | 3728 | 85.70 | 0 | |
| GA INFRA - BABA (JV) | 1028 | 2226 | 194 | 3448 | 1010 | 2180 | 184 | 3374 | 97.85 | 0 | |||
| 17 |
Hardoi |
NCC Ltd. | 1329 | 1616 | 1313 | 4258 | 996 | 1279 | 1165 | 3440 | 80.79 | 0 | 1)Major cracks seen on boundary wall. 2)Pea gravel not stacked properly at site. 3)FHTC installed outside the house. 3) Disinfection of pipe not done 4) Lifting appliances, lifting gears and Compressor was not inspected by competent agency 5) Test certificate scaffolding material not submitted.6) Nonstandard scaffolding used at site.7) Non-standard DG used at site.7) Quality issues during OHT work |
| 18 |
Sonbhadra |
VPRPL | 165 | 2567 | 98 | 2830 | 165 | 2284 | 68 | 2517 | 88.94 | 0 | |
| NCC Ltd. | 109 | 1920 | 23 | 2052 | 109 | 1745 | 20 | 1874 | 91.33 | 0 | |||
| Larsen & Toubro Ltd | 47 | 1802 | 62 | 1911 | 47 | 1455 | 43 | 1545 | 80.85 | 0 | |||
| GVPR | 119 | 1260 | 40 | 1419 | 119 | 1054 | 23 | 1196 | 84.28 | 0 | |||
| Jain Const. | 9 | 176 | 14 | 199 | 9 | 176 | 14 | 199 | 100.00 | 0 | |||
| 19 |
Lucknow |
NCC Ltd. | 202 | 1679 | 553 | 2434 | 88 | 820 | 553 | 1461 | 60.02 | 0 | |
| 20 |
Ballia |
GAJA - GAIPL JV | 253 | 1495 | 6 | 1754 | 239 | 1365 | 5 | 1609 | 91.73 | 0 | 1- Compaction not done after backfilling .pipe laying work is completed, trench is backfilled haphazardly without any proper layering , watering and Compaction which is not as per clause no-8.1.2 of Indian Standard 7634:2012 (part-2) 2. Depth of the trench observed is 470mm at the top of the 63mm HDPE Pipe whereas as per DPR the Depth should be at least 1000mm+ of pipe |
| Larsen & Toubro Ltd | 426 | 1061 | 10 | 1497 | 420 | 962 | 10 | 1392 | 92.99 | 0 | 1.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents.Proper finishing not found of OHT Stair .2.Curing not properly done 3. Trench has been found settled, After pipe laying work compaction must be done in layer wise using compactor. | ||
| Eagle Infra- Sudhakara Infra JV | 265 | 779 | 10 | 1054 | 255 | 685 | 10 | 950 | 90.13 | 0 | 1.Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents..2.Curing not properly done 3.After pipe laying work compaction must be done in layer wise using compactor. | ||
| 21 |
Lakhimpur Kheri |
NCC Ltd. | 393 | 733 | 121 | 1247 | 129 | 532 | 90 | 751 | 60.22 | 0 | 1- Grouting work not completed in ZnAl tank, 2- Major honeycombing observed in OHT. |
| Vindhya-GAJA (JV) | 201 | 379 | 91 | 671 | 71 | 221 | 61 | 353 | 52.61 | 0 | 1- Honeycombing found in OHT column & brace beam, 2- Poor quality of workmanship in oht work. | ||
| 22 |
Lalitpur |
M/s Sudhakara Infratech Pvt. Ltd | 67 | 55 | 829 | 951 | 67 | 55 | 741 | 863 | 90.75 | 0 | |
| JMC-JWIL (JV) | 48 | 66 | 413 | 527 | 48 | 66 | 344 | 458 | 86.91 | 0 | |||
| DARA ENGINEERING | 45 | 79 | 348 | 472 | 45 | 79 | 302 | 426 | 90.25 | 0 | |||
| Banko Ganga | 5 | 10 | 85 | 100 | 5 | 10 | 74 | 89 | 89.00 | 0 | |||
| Brija Banco Pvt. Ltd | 10 | 18 | 52 | 80 | 10 | 18 | 31 | 59 | 73.75 | 0 | |||
| 23 |
Raebareli |
NCC Ltd. | 47 | 428 | 78 | 553 | 44 | 428 | 78 | 550 | 99.46 | 0 | Honey combing found in OHT, Leakage observed in OHT |
| Vindhya-GAJA (JV) | 36 | 211 | 20 | 267 | 26 | 195 | 20 | 241 | 90.26 | 0 | Poor quality of workmanship in OHT work, Leakage found in pipeline, Honey combing found in OHT. | ||
| 24 |
Basti |
Megha | 117 | 181 | 188 | 486 | 92 | 106 | 117 | 315 | 64.81 | 0 | |
| JAKSON - VISHVARAJ (JV) | 11 | 35 | 24 | 70 | 6 | 29 | 20 | 55 | 78.57 | 0 | |||
| VSA | 6 | 11 | 14 | 31 | 6 | 10 | 12 | 28 | 90.32 | 0 | |||
| 25 |
Jhansi |
BGCCPL-Ramky (JV) | 29 | 140 | 303 | 472 | 29 | 102 | 196 | 327 | 69.28 | 0 | |
| NCC Ltd. | 26 | 93 | 295 | 414 | 26 | 93 | 269 | 388 | 93.72 | 0 | |||
| Indian Hume Pipe | 16 | 40 | 65 | 121 | 16 | 40 | 56 | 112 | 92.56 | 0 | |||
| DARA ENGINEERING | 19 | 31 | 62 | 112 | 19 | 31 | 58 | 108 | 96.43 | 0 | |||
| Unipro | 20 | 28 | 50 | 98 | 20 | 28 | 48 | 96 | 97.96 | 0 | |||
| 26 |
Saharanpur |
GA INFRA - BABA (JV) | 88 | 248 | 17 | 353 | 61 | 119 | 16 | 196 | 55.52 | 0 | Poor Quality work OHT 3rd brace beam & column not plumb. Without complete staircase work & plumb of brace beam Inappropriate size of staircase Poor Quality work OHT column found honeycomb |
| NKG-PRIMUS (JV) | 9 | 117 | 6 | 132 | 6 | 70 | 3 | 79 | 59.85 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. | ||
| Gayatri Projects LTD | 10 | 117 | 2 | 129 | 6 | 23 | 0 | 29 | 22.48 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. | ||
| 27 |
Sultanpur |
Vindhya-GAJA (JV) | 75 | 127 | 134 | 336 | 59 | 57 | 70 | 186 | 55.36 | 0 | |
| Gayatri Projects LTD | 19 | 19 | 18 | 56 | 13 | 10 | 14 | 37 | 66.07 | 0 | |||
| UNIVERSAL MEP | 13 | 11 | 13 | 37 | 13 | 11 | 13 | 37 | 100.00 | 0 | |||
| 28 |
Sitapur |
NCC Ltd. | 317 | 0 | 0 | 317 | 18 | 0 | 0 | 18 | 5.68 | 0 | |
| Larsen & Toubro Ltd | 0 | 46 | 110 | 156 | 0 | 24 | 60 | 84 | 53.85 | 0 | |||
| 29 |
Hathras |
BGCCPL-Ramky (JV) | 43 | 84 | 184 | 311 | 31 | 60 | 152 | 243 | 78.14 | 0 | |
| ION EXCHANGE | 11 | 21 | 14 | 46 | 10 | 19 | 14 | 43 | 93.48 | 0 | Work done without RFI & Reinstatement work not as per standard specification | ||
| 30 |
Kasganj |
ION EXCHANGE | 51 | 156 | 72 | 279 | 35 | 128 | 54 | 217 | 77.78 | 0 | |
| PNC-SPML-JV | 48 | 145 | 71 | 264 | 35 | 128 | 54 | 217 | 82.20 | 0 | |||
| 31 |
Muzaffarnagar |
JMC - Lakshmi (JV) | 149 | 108 | 14 | 271 | 89 | 41 | 2 | 132 | 48.71 | 0 | - |
| NKG-PRIMUS (JV) | 62 | 26 | 3 | 91 | 25 | 1 | 0 | 26 | 28.57 | 0 | - | ||
| Gayatri Projects LTD | 2 | 4 | 0 | 6 | 2 | 4 | 0 | 6 | 100.00 | 0 | - | ||
| 32 |
Firozabad |
Larsen & Toubro Ltd | 5 | 251 | 7 | 263 | 5 | 190 | 7 | 202 | 76.81 | 0 | |
| NCC Ltd. | 0 | 153 | 1 | 154 | 0 | 149 | 1 | 150 | 97.40 | 0 | |||
| 33 |
Amroha |
OMIL-JWIL (JV) | 90 | 121 | 44 | 255 | 80 | 117 | 41 | 238 | 93.33 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT 6) Zinc alum tank leakage |
| SPML Infra | 85 | 91 | 36 | 212 | 61 | 84 | 31 | 176 | 83.02 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
| LC INFRA | 3 | 2 | 3 | 8 | 2 | 2 | 3 | 7 | 87.50 | 0 | 1)Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
| 34 |
Siddharth Nagar |
Megha | 59 | 174 | 17 | 250 | 51 | 157 | 5 | 213 | 85.20 | 0 | |
| JAKSON - VISHVARAJ (JV) | 55 | 14 | 69 | 138 | 45 | 12 | 57 | 114 | 82.61 | 0 | |||
| VSA | 29 | 85 | 7 | 121 | 23 | 85 | 1 | 109 | 90.08 | 0 | |||
| 35 |
Budaun |
PNC-SPML-JV | 75 | 149 | 8 | 232 | 75 | 149 | 8 | 232 | 100.00 | 0 | |
| NCC Ltd. | 3 | 4 | 2 | 9 | 3 | 4 | 2 | 9 | 100.00 | 0 | |||
| 36 |
Jalaun |
BGCCPL-Ramky (JV) | 118 | 80 | 32 | 230 | 47 | 27 | 12 | 86 | 37.39 | 17 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. |
| GVPR | 40 | 40 | 16 | 96 | 29 | 26 | 12 | 67 | 69.79 | 18 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. | ||
| 37 |
Moradabad |
LC INFRA | 40 | 20 | 169 | 229 | 40 | 17 | 164 | 221 | 96.51 | 0 | Cube Test Not Conduct Properly 07 days & 28 days , Approved Drawing Not Avaliable at site , Majorcracks seen on Boundary wall , PPE Kit Not avaliable at site & Saftey Negligence during dome casting. |
| NKG-PRIMUS (JV) | 33 | 27 | 112 | 172 | 30 | 22 | 102 | 154 | 89.53 | 0 | Staging Done Without Staircase , Brick Quality is not good & Saftey negligence during dome casting. | ||
| 38 |
Agra |
Megha | 172 | 39 | 9 | 220 | 99 | 24 | 5 | 128 | 58.18 | 0 | |
| NCC-APCO JV | 56 | 26 | 6 | 88 | 53 | 25 | 6 | 84 | 95.45 | 0 | |||
| 39 |
Kannauj |
VSA | 43 | 78 | 79 | 200 | 40 | 75 | 70 | 185 | 92.50 | 0 | ZN-AL tank Fusion Not Done, Road Restoration Not Done, Column misalignment observed, honeycomb observed, work Without RFI |
| GVPR | 19 | 59 | 40 | 118 | 18 | 56 | 32 | 106 | 89.83 | 0 | Road Restoration Not Done, honeycomb observed, work Without RFI | ||
| 40 |
Ambedkar Nagar |
Vindhya-GAJA (JV) | 56 | 130 | 3 | 189 | 56 | 86 | 2 | 144 | 76.19 | 0 | |
| Welspun Kaveri Infraprojects JV | 11 | 30 | 2 | 43 | 10 | 16 | 2 | 28 | 65.12 | 0 | |||
| 41 |
Etah |
Power Mech Projects Ltd | 12 | 78 | 95 | 185 | 12 | 47 | 65 | 124 | 67.03 | 0 | |
| JMC - Lakshmi (JV) | 4 | 25 | 26 | 55 | 3 | 16 | 18 | 37 | 67.27 | 0 | |||
| ION EXCHANGE | 0 | 4 | 0 | 4 | 0 | 3 | 0 | 3 | 75.00 | 0 | |||
| 42 |
Sant Kabeer Nagar |
Megha | 29 | 88 | 55 | 172 | 10 | 24 | 22 | 56 | 32.56 | 0 | It was found at the site there is a large gap between the precast columns and the beam of OHT. Whereas gap should be 25 mm as per approved OHT Drawing. As per IS 15916 -2011, ±10 % tolerance allowed in precast components. Precast OHT Column dowel bars found 410 mm instead of 500 mm. Zinc Aluminum tank is corroded, Large gap between OHT slab and hold down bracket. |
| JAKSON - VISHVARAJ (JV) | 22 | 74 | 61 | 157 | 20 | 23 | 13 | 56 | 35.67 | 0 | Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing. Alignment of beam is not as per drawing and design. | ||
| VISHVARAJ | 16 | 43 | 45 | 104 | 15 | 20 | 7 | 42 | 40.38 | 0 | Not proper finishing work of OHT column and brace , patching found at many places . Column not in an alighnment. At joints of column and brace lots of honey comb found . Column casting done without using plumb bob.OHT column above third brace is tilt. | ||
| 43 |
Kanpur Nagar |
Vindhya-GAJA (JV) | 74 | 35 | 52 | 161 | 71 | 35 | 52 | 158 | 98.14 | 0 | |
| VSA | 28 | 21 | 34 | 83 | 23 | 21 | 34 | 78 | 93.98 | 0 | |||
| 44 |
Aligarh |
PNC-SPML-JV | 15 | 118 | 9 | 142 | 15 | 114 | 9 | 138 | 97.18 | 0 | |
| JMC - Lakshmi (JV) | 12 | 85 | 2 | 99 | 12 | 84 | 1 | 97 | 97.98 | 0 | |||
| ION EXCHANGE | 12 | 51 | 14 | 77 | 12 | 48 | 14 | 74 | 96.10 | 0 | |||
| 45 |
Bareilly |
NCC Ltd. | 42 | 60 | 36 | 138 | 38 | 59 | 36 | 133 | 96.38 | 0 | Slab casting done without permission, and columns above TB-3 without permission of UPJN and TPIA |
| 46 |
Bahraich |
PNC-SPML-JV | 44 | 76 | 18 | 138 | 44 | 70 | 16 | 130 | 94.20 | 0 | 1. Piling work is being done without approval of Methodology . 2. As build drawing not submitted to UPJN and TPI also |
| GA INFRA-VPL | 9 | 14 | 8 | 31 | 5 | 12 | 8 | 25 | 80.65 | 0 | HDD Method is not implementing in possible site locations 2. Lack of proper road restoration works. 3. Lack of manpower, physical work progress is very slow. 4. As build drawing not submitted to UPJN office and to TPI also. | ||
| 47 |
Shamli |
JMC - Lakshmi (JV) | 54 | 70 | 9 | 133 | 30 | 12 | 6 | 48 | 36.09 | 0 | |
| Gayatri Projects LTD | 2 | 4 | 2 | 8 | 2 | 0 | 0 | 2 | 25.00 | 0 | |||
| 48 |
Barabanki |
Megha | 75 | 54 | 2 | 131 | 39 | 17 | 1 | 57 | 43.51 | 0 | |
| PNC-SPML-JV | 53 | 50 | 2 | 105 | 43 | 25 | 1 | 69 | 65.71 | 0 | |||
| Vindhya-GAJA (JV) | 28 | 22 | 0 | 50 | 22 | 16 | 0 | 38 | 76.00 | 0 | |||
| VSA | 12 | 13 | 0 | 25 | 12 | 6 | 0 | 18 | 72.00 | 0 | |||
| Gayatri Projects LTD | 5 | 9 | 0 | 14 | 4 | 1 | 0 | 5 | 35.71 | 0 | |||
| 49 |
Farrukhabad |
GVPR | 33 | 54 | 39 | 126 | 21 | 38 | 15 | 74 | 58.73 | 0 | |
| Vindhya-GAJA (JV) | 2 | 35 | 21 | 58 | 2 | 31 | 21 | 54 | 93.10 | 0 | |||
| 50 |
Gonda |
KLSR - RAYS (JV) | 54 | 40 | 27 | 121 | 35 | 18 | 13 | 66 | 54.55 | 0 | Misalignment, Major Honeycomb, Road Restoration, Cube Test Fail and water supply without Chlorination. Cracks in Plinth protection and BW. |
| Larsen & Toubro Ltd | 2 | 48 | 17 | 67 | 2 | 39 | 9 | 50 | 74.63 | 0 | Road Restoration and water supply without chlorination. | ||
| 51 |
Pilibhit |
PNC-SPML-JV | 27 | 30 | 60 | 117 | 27 | 30 | 60 | 117 | 100.00 | 0 | all compliances have been submitted by the firm. |
| VISHVARAJ | 11 | 16 | 49 | 76 | 11 | 16 | 49 | 76 | 100.00 | 0 | |||
| 52 |
Mainpuri |
NCC Ltd. | 25 | 62 | 19 | 106 | 16 | 54 | 17 | 87 | 82.08 | 0 | |
| 53 |
Auraiya |
GVPR | 69 | 29 | 6 | 104 | 68 | 29 | 6 | 103 | 99.04 | 0 | |
| Indian Hume Pipe | 9 | 14 | 3 | 26 | 9 | 13 | 3 | 25 | 96.15 | 0 | |||
| 54 |
Ayodhya |
VSA | 38 | 44 | 22 | 104 | 28 | 20 | 10 | 58 | 55.77 | 0 | |
| UNIVERSAL MEP | 2 | 25 | 10 | 37 | 2 | 25 | 9 | 36 | 97.30 | 0 | |||
| Vindhya-GAJA (JV) | 8 | 15 | 7 | 30 | 5 | 12 | 5 | 22 | 73.33 | 0 | |||
| Gayatri Projects LTD | 5 | 14 | 4 | 23 | 5 | 13 | 4 | 22 | 95.65 | 0 | |||
| 55 |
Hamirpur |
JWIL | 5 | 4 | 86 | 95 | 5 | 4 | 86 | 95 | 100.00 | 0 | |
| PNC-SPML-JV | 6 | 4 | 68 | 78 | 6 | 4 | 68 | 78 | 100.00 | 0 | |||
| 56 |
Etawah |
Indian Hume Pipe | 24 | 42 | 20 | 86 | 24 | 42 | 20 | 86 | 100.00 | 0 | |
| OMIL-JWIL (JV) | 39 | 17 | 4 | 60 | 28 | 17 | 4 | 49 | 81.67 | 0 | |||
| 57 |
Sambhal |
SPML Infra | 20 | 30 | 35 | 85 | 16 | 10 | 15 | 41 | 48.24 | 0 | Zinc-Alum tank,Location and position of nut bolt is not as per specification,Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.Column beam misalignment. Honey comb |
| NKG-PRIMUS (JV) | 15 | 30 | 38 | 83 | 12 | 11 | 13 | 36 | 43.37 | 0 | Zinc-Alum tank, Location and position of nut bolt is not as per specification, Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.honey comb,steel exposer. | ||
| LC INFRA | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | |||
| 58 |
Banda |
Larsen & Toubro Ltd | 9 | 9 | 67 | 85 | 9 | 9 | 67 | 85 | 100.00 | 0 | |
| NCC Ltd. | 9 | 11 | 29 | 49 | 9 | 11 | 29 | 49 | 100.00 | 0 | |||
| 59 |
Amethi |
Vindhya-GAJA (JV) | 19 | 33 | 29 | 81 | 19 | 21 | 14 | 54 | 66.67 | 0 | |
| Gayatri Projects LTD | 14 | 24 | 28 | 66 | 14 | 13 | 12 | 39 | 59.09 | 0 | |||
| Welspun Kaveri Infraprojects JV | 11 | 13 | 20 | 44 | 11 | 10 | 16 | 37 | 84.09 | 0 | |||
| 60 |
Balrampur |
Larsen & Toubro Ltd | 13 | 30 | 32 | 75 | 10 | 27 | 30 | 67 | 89.33 | 0 | Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. 2) Pump house finishing work is not proper. 3) Lot of road restoration work is pending from the agency and quality of road restoration is not as per standard. 4. As build drawing not submitted to UPJN and TPI. |
| Dara- Eco Protection (JV) | 14 | 25 | 22 | 61 | 11 | 22 | 21 | 54 | 88.52 | 0 | Plywood doors have been installed in 17 Gram Panchayats. 2) HDD Method is not implementing in possible site locations. 3. Hydrotesting, disinfection, and flushing of the pipeline not done before water supply. 4. As build drawing not submitted to UPJN and TPI. | ||
| 61 |
Shahjahanpur |
NCC Ltd. | 18 | 29 | 25 | 72 | 18 | 27 | 22 | 67 | 93.06 | 0 | |
| 62 |
Kanpur Dehat |
VSA | 27 | 18 | 23 | 68 | 26 | 18 | 23 | 67 | 98.53 | 0 | |
| GVPR | 4 | 9 | 10 | 23 | 4 | 9 | 10 | 23 | 100.00 | 0 | |||
| Indian Hume Pipe | 5 | 5 | 10 | 20 | 5 | 5 | 10 | 20 | 100.00 | 0 | |||
| Vindhya-GAJA (JV) | 2 | 5 | 2 | 9 | 1 | 5 | 2 | 8 | 88.89 | 0 | |||
| 63 |
Mahoba |
JMC-JWIL (JV) | 13 | 27 | 24 | 64 | 13 | 27 | 24 | 64 | 100.00 | 0 | |
| SLC-SMC (JV) | 7 | 16 | 12 | 35 | 7 | 15 | 12 | 34 | 97.14 | 0 | |||
| Larsen & Toubro Ltd | 6 | 14 | 12 | 32 | 6 | 14 | 12 | 32 | 100.00 | 0 | |||
| N.K. Gupta & K.B. Gupta Contractors | 6 | 10 | 8 | 24 | 6 | 10 | 8 | 24 | 100.00 | 0 | |||
| 64 |
Bulandshahr |
JMC - Lakshmi (JV) | 1 | 59 | 2 | 62 | 1 | 59 | 2 | 62 | 100.00 | 0 | |
| Welspun Kaveri Infraprojects JV | 0 | 24 | 1 | 25 | 0 | 24 | 0 | 24 | 96.00 | 0 | |||
| Power Mech Projects Ltd | 2 | 10 | 1 | 13 | 2 | 10 | 1 | 13 | 100.00 | 0 | |||
| 65 |
Rampur |
OMIL-JWIL (JV) | 19 | 27 | 3 | 49 | 15 | 19 | 2 | 36 | 73.47 | 0 | RFI was not raised. 2.Quality of material not as per specification.3. Safety norms not followed, approved drawing not at site. |
| NKG-PRIMUS (JV) | 12 | 22 | 6 | 40 | 9 | 13 | 0 | 22 | 55.00 | 0 | OHT construction, cube testing failure, CC road restoration done work without raised RFI, OHT column beam misalignment, staircase not as per drawing | ||
| LC INFRA | 1 | 4 | 0 | 5 | 1 | 2 | 0 | 3 | 60.00 | 0 | Brick Quality is not good 2.Poor workmanship3.Caution Tape not used 4. Safety belt not used during OHT heighted work 5.PPE kit not used. | ||
| SPML Infra | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | |||
| 66 |
Bijnor |
Vindhya-GAJA (JV) | 23 | 6 | 19 | 48 | 22 | 4 | 15 | 41 | 85.42 | 0 | un approved steel and cement,column alignment not in plumb,major honeycombs. |
| LC INFRA | 7 | 3 | 4 | 14 | 7 | 2 | 4 | 13 | 92.86 | 0 | column alignment not in plumb,major honeycombs,brace beam shuttering found bulge. | ||
| 67 |
Chitrakoot |
Larsen & Toubro Ltd | 9 | 16 | 20 | 45 | 9 | 15 | 16 | 40 | 88.89 | 0 | |
| GVPR | 5 | 6 | 21 | 32 | 5 | 3 | 16 | 24 | 75.00 | 0 | |||
| 68 |
Shravasti |
Larsen & Toubro Ltd | 13 | 18 | 13 | 44 | 11 | 15 | 13 | 39 | 88.64 | 0 | 1) Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. Many schemes HDPE Pipe distribution line is found open without providing end caps. 2. Site Order Book , Approved drawings are not available at site premise during execution. 3. As build drawing not submitted to UPJN and TPI. |
| GA INFRA-VPL | 0 | 33 | 0 | 33 | 0 | 12 | 0 | 12 | 36.36 | 0 | Cube fail -2 / Honeycomb -3 / Water logged -1 / Steel cut upto GL -1 / Steel rusted -5 | ||
| 69 |
Meerut |
Power Mech Projects Ltd | 3 | 32 | 2 | 37 | 3 | 32 | 1 | 36 | 97.30 | 0 | |
| 70 |
Baghpat |
LC INFRA | 4 | 10 | 18 | 32 | 4 | 10 | 14 | 28 | 87.50 | 0 | |
| 71 |
Hapur |
LC INFRA | 4 | 4 | 19 | 27 | 4 | 4 | 19 | 27 | 100.00 | 0 | |
| 72 |
Mathura |
NCC-APCO JV | 9 | 11 | 0 | 20 | 6 | 10 | 0 | 16 | 80.00 | 0 | 3 NCR pending as critical and 1NCR as Major |
| 73 |
Ghaziabad |
LC INFRA | 4 | 12 | 3 | 19 | 4 | 7 | 2 | 13 | 68.42 | 0 | |
| 74 |
Gautam Buddha Nagar |
LC INFRA | 2 | 2 | 13 | 17 | 1 | 2 | 8 | 11 | 64.71 | 0 | |