| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20012442 | Bhuwalpur Sisni GP Water Supply Scheme | 20012442/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Lap provided in non-lapping Zone | |||||||||||||
| 2 | 20085623 | Gora Ubarani Water Supply Scheme | 20085623/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | One or more RCC columns appear not vertically plumb when observed from the side angle | |||||||||||||
| 3 | 20090886 | Kathgar Water Supply Scheme | 20090886-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | lt has been observed that the column above 3rd brace beams have undergone extensive repairs and are misaligned. | |||||||||||||
| 4 | 20012772 | Jariya GP Water Supply Scheme | 20012772-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | lt has been observed through visual inspection that the one column above 1st and 2nd brace beams are misaligned, | |||||||||||||
| 5 | 20062178 | JAHANPUR KODAR WATER SUPPLY SCHEME | 20062178-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | lt has been observed through visual inspection that the one column above 1st and 2nd brace beams are misaligned, | |||||||||||||
| 6 | 20094592 | Lakhanpur Water Supply Scheme | 20094592-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | From visual inspection, the column appears to be misaligned. The change in its profile and the eccentricity near the beam connection suggest that the column may not be perfectly vertical or centered. | |||||||||||||
| 7 | 20090875 | SAWANPUR NEWADA Water Supply Scheme | 20090875-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | From visual inspection, the column appears to be misaligned. The change in its profile and the eccentricity near the beam connection suggest that the column may not be perfectly vertical or centered. | |||||||||||||
| 8 | 8362069 | JARIYARI | 8362069-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | From visual inspection, the column appears to be misaligned. The change in its profile and the eccentricity near the beam connection suggest that the column may not be perfectly vertical and Honeycombing also found in Ring beam and Column." | |||||||||||||
| 9 | 8362109 | PAHARPUR KAHSO | 8362109-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Column above TB2 and TB3 appears to be misaligned from visual inspection. | |||||||||||||
| 10 | 20064090 | Khanuwa WATER SUPPLY SCHEME | 20064090/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | It was observed that 02 columns appear to be misaligned from the intended alignment. Futhermore, improper linishing was observed at the colurnn-beam junction. | |||||||||||||
| 11 | 20012459 | Rampur Kasiha GP Water Supply Scheme | 20012459/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | From visual inspection, the column appears to be misaligned. | |||||||||||||
| 12 | 8362090 | SARAIDAMU | 8362090-OHT-01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | From visual inspection 2 columns appear to be misaligned from the intended alignment. Furthermore, improper finishing was observed at the column-beam junction. | |||||||||||||
| 13 | 8362072 | SEMRA | 8362072-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 14 | 8362192 | BAGHAIL | 8362192-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | • Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 15 | 20090255 | BEWAL WATER SUPPLY | 20090255/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | • Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 16 | 20090251 | BARARA BUJURG Water Supply Scheme | 20090251-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | • Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 17 | 8361895 | SEONTHI | 8361895-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 18 | 8388533 | Jamuvava | 8388533/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 19 | 20062204 | ADILABAD WATER SUPPLY SCHEME | 20062204/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 20 | 20064074 | Tanda WATER SUPPLY SCHEME | 20064074-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 21 | 20062206 | SENDURA MAU WATER SUPPLY SCHEME | 20062206/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. • After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 22 | 8361878 | AGHAURA | 8361878-OHT-01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Resolved | The leakage observed in the Zinc–Alum water storage tanks has been successfully rectified. All seepage points were identified and repaired by tightening/replacing bolts, installing new neoprene/rubber washers, and applying food-grade internal sealant and external waterproof sealant to the affected joints. Stagnant water around the tank base was removed, the slab surface was cleaned and restored, and necessary waterproofing was carried out to prevent future seepage. After completion of the repair works, the tank was refilled and monitored for 24 hours. No leakage or seepage was observed during the testing period. The tank is now functioning normally, with proper water pressure restored to the distribution system. | ||||||||||||
| 23 | 20090632 | BATHUWA KHAS Water Supply Scheme | 20090632/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1.The reinforcement bars were thoroughly cleaned using wire brushes to remove loose rust, scale, and foreign materials. 2.After proper surface preparation, Nito Zinc Primer was applied as per manufacturer’s specifications. | ||||||||||||
| 24 | 8361872 | SARAI MUBARAK | 8361872/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1.The reinforcement bars were thoroughly cleaned using wire brushes to remove loose rust, scale, and foreign materials. 2.After proper surface preparation, Nito Zinc Primer was applied as per manufacturer’s specifications. | ||||||||||||
| 25 | 20062147 | SONIKA MAU WATER SUPPLY SCHEME | 20062147-OHT-01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1.The reinforcement bars were thoroughly cleaned using wire brushes to remove loose rust, scale, and foreign materials. 2.After proper surface preparation, Nito Zinc Primer was applied as per manufacturer’s specifications. | ||||||||||||
| 26 | 20090826 | RAHWAN Water Supply Scheme | 20090826-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 27 | 20089929 | Dalmau Water Supply Scheme | 20089929-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1. Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 28 | 8360965 | Chandauli | 8360965/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1.The reinforcement bars were thoroughly cleaned using wire brushes to remove loose rust, scale, and foreign materials. 2.After proper surface preparation, Nito Zinc Primer was applied as per manufacturer’s specifications. | ||||||||||||
| 29 | 8362286 | HIDAIN | 8362286/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Resolved | The leakage observed in the Zinc–Alum water storage tanks has been successfully rectified. All seepage points were identified and repaired by tightening/replacing bolts, installing new neoprene/rubber washers, and applying food-grade internal sealant and external waterproof sealant to the affected joints. Stagnant water around the tank base was removed, the slab surface was cleaned and restored, and necessary waterproofing was carried out to prevent future seepage. After completion of the repair works, the tank was refilled and monitored for 24 hours. No leakage or seepage was observed during the testing period. The tank is now functioning normally, with proper water pressure restored to the distribution system | ||||||||||||
| 30 | 20090029 | Kamalpur Water Supply Scheme | 20090029/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 31 | 20014907 | Maha Khera GP Water Supply Scheme | 20014907/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1.Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 32 | 20062207 | JHARAHA WATER SUPPLY SCHEME | 20062207/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | 1.Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 33 | 8360623 | Padri Ganeshpur | 8360623-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 34 | 20064084 | Baghai Ahalwar WATER SUPPLY SCHEME | 20064084-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 35 | 8360622 | Chandwal | 8360622-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2 .After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 36 | 8362499 | SULTANPUR | 8362499/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 37 | 20017220 | Baitu GP Water Supply Scheme | 20017220-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 38 | 20022721 | Ekauni GP Water Supply Scheme | 20022721/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Rectification has been completed by removing loose concrete, cleaning the exposed reinforcement, applying anti-corrosion treatment/zinc-rich primer, and restoring the affected portion with suitable repair mortar. NDT testing has also been carried out after repair, and proper finishing and curing have been ensured. | ||||||||||||
| 39 | 20092516 | Purasi Water Supply Scheme | 20092516/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 40 | 8362389 | KUNDAULI | 8362389-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 41 | 20066102 | Sarai Dugosha Water Supply Scheme | 20066102-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 42 | 8362388 | BANNAWA | 8362388-OHT-01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Poor finishing has been rectified and proper surface finishing has been achieved at the affected locations. Visible air voids have been repaired, and the embedded shuttering material at the slab bottom has been removed. Surface preparation and repainting have been carried out properly after rectification | ||||||||||||
| 43 | 20087184 | Surasana Water Supply Scheme | 20087184-OHT-01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Resolved | Liner of Zinc Alum Tank has been changed. | ||||||||||||
| 44 | 20062140 | BADAWAR WATER SUPPLY SCHEME | 20062140-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 45 | 8362130 | BAHUDA KHURD | 8362130/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 46 | 8360916 | Jagjiwanpur Amariya | 8360916/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted | ||||||||||||
| 47 | 20012294 | Kumbhi GP Water Supply Scheme | 20012294-OHT-01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | 1.Rectification has been completed by removing loose concrete, cleaning the exposed reinforcement, applying anti-corrosion treatment/zinc-rich primer, and restoring the affected portion with suitable repair mortar. 2.NDT testing has also been carried out after repair, and proper finishing and curing have been ensured | ||||||||||||
| 48 | 20011312 | Manehroo GP Water Supply Scheme | 20011312-OHT-01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Honeycombing was repaired by applying Nitobond as a bonding agent, filling cavities with Conbextra GP2. 2.After proper curing, an Ultrasonic Pulse Velocity (UPV) test was conducted. | ||||||||||||
| 49 | 20013146 | Bisaiyya GP Water Supply Scheme | 20013146/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Rectification has been completed by removing loose concrete, cleaning the exposed reinforcement, applying anti-corrosion treatment/zinc-rich primer, and restoring the affected portion with suitable repair mortar. NDT testing has also been carried out after repair, and proper finishing and curing have been ensured | ||||||||||||
| 50 | 20012584 | Pindauli GP Water supply Scheme | 20012584/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Rectification has been completed by removing loose concrete, cleaning the exposed reinforcement, applying anti-corrosion treatment/zinc-rich primer, and restoring the affected portion with suitable repair mortar. NDT testing has also been carried out after repair, and proper finishing and curing have been ensured | ||||||||||||