Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20043840 Alipur 20043840/01 No No No No No No Yes No No No No No No Resolved Poor scaffolding work was done by using poor quality bamboo for OHT construction work. This type of work affect the quality of structure and also it may reason of collapse of structure during execution of work.(poor scaffolding removed from site)
2 20043841 Baharoli 20043841/01 No No No No Yes No No No No No No No No Resolved Lap length has not been maintained by TKC in vertical bars of staircase column of OHT and also its not found in alternate basis as per norms.
3 20043846 Khadara 20043846/01 No Yes No No No No No No No No No No No Resolved It has been observed that during visit as per visual inspection first brace beam of staircase not vertically aligned. (dismantling has been done.)
4 20043855 Umarghana 20043855/01 No No No No Yes No No No No No No No No Resolved Vertical steel bars of OHT staircase column at plinth level have been found cut. It is difficult to provide steel bars with proper development length. Take corrective action regarding this issue before starting the further work on OHT staircase at site.(development length has been provided after dismantling of column)
5 20045365 Sujawalpur & Kansahi 20045365/01 No No No No No No Yes No No No No No No Resolved Water has been accumulated over the foundation of OHT. This may cause the uneven settlement of soil below the raft. And also work has been stopped for 3 months.(De watering completed)
6 20061345 JINDPUR 20061345/01 No No No No Yes No No No No No No No No Resolved Overlapping of steel bar has not been given properly. Ref. Approved drawing & IS 456:2000(Reinforcement provided as per drawing)
7 20062599 AJMATPUR 20062599/01 No No Yes No No No No No No No No No No Resolved The core cutting test of the raft foundation of OHT was done by IIT Kanpur seven months ago and its strength was found to be unsatisfactory. After this, EE sir had instructed to TKC its demolition. The work of its demolition has not been done by TKC till(Old Raft dismantled and new OHT under construction)
8 20062932 PILKHINI 20062932/01 No No No No Yes No No No No No No No No Resolved The size of the risers and the last flight of stairs has not been done as per the drawing.(After dismantling, reconstruction work done)
9 20068281 HARIRAMPUR,HARIYAPUR 20068281/01 No Yes No No No No No No No No No No No Resolved Column has not been found in plumb and the second lift column above 3rd brace seems shifted approx 30mm.(by plumbing verticality check found ok)
10 20068380 BAKANDHA 20068380/01 No No No No No No Yes No No No No No No Resolved Casting starts without performing material testing. As per visual inspection poor quality of sand found at site.(material test report provided )
11 20075581 Souh &Chintapur 20075581/01 No No No No No No Yes No No No No No No Resolved Raft of OHT has been constructed without raising/verification of RFI and also material testing was not done.(material test was performed and report provided.)
12 20079106 BARHAT 20079106/01 No No No No No No Yes No No No No No No Resolved Curing of OHT is not being done properly during inspection.(Curing is going on at the time of OHT under construction)
13 20089204 SARAYDHARAMPUR 20089204/01 No No No No No No Yes No No No No No No Resolved After binding the bars, the OHT work has stopped for the last one month and due to the OHT trench being filled with water, it is in contact with water, which will affect its quality. (reinforcement replaced before casting work)
14 20089216 BIJURI 20089216/01 No No No No No No Yes No No No No No No Resolved Water logged over the foundation of OHT. Work has been stopped for more than 15 days.(Dewatering has been done )
15 20089367 JONIHA 20089367/01 No No No No Yes No No No No No No No No Resolved it has been found that Overlaps are provided in consecutive order in raft foundation of OHT. TKC is requested to provide it in alternate order as per the standard.(Reinforcement provided as per drawing)
16 20095897 Rasoolpur & Jagatpur 20095897/01 No Yes No No Yes No Yes No No No No No No Resolved Resolved Resolved 1.Tread and riser of OHT has not been made as per drawing and finishing is also not done properly.(After dismantling ,re-constructed of Riser and trade as per drawing specification.) 2.Alignment of 3rd flight of staircase has not been found properly. Dismantle it and reconstruct again in proper alignment.(After dismantling ,re-constructed 3rd flight of staircase as per drawing specification.) 3.Crack has been developed in the 2nd landing of staircase.(After dismantling ,re-constructed 2nd landing of staircase. as per drawing specification.)
17 20095909 SANGRAMPUR,BHAKRANA 20095909/01 No No No No Yes No No No No No No No No Resolved Spacing between columns to 1st stirrup has been found 250 mm instead of 100 in foundation ring beam of OHT at site.(Spacing between columns to 1st stirrup has been provided as per drawing)
18 20097485 UMARA 20097485/01 No No No No Yes No No No No No No No No Resolved 4th flight staircase of OHT was not constructed properly as per drawing.
19 20097515 HASWA 20097515/01 No No No No No No Yes No No No No No No Resolved seepage has been observed at near ring beam bottom dome of over head tank.(epoxy/ water proofing done and hydrotest also perfomed)
20 20097849 OTI 20097849/01 No No No No Yes No No No No No No No No Resolved The width of tread of OHT staircase has been found 230 mm instead of 250 mm as per approved drawing.(With help motar chipping work)
21 20097920 TRILOCHANPUR 20097920/01 No No Yes No No No No No No No No No No Resolved Raft foundation cube test result of 7&28 days are not fulfilling the acceptance criteria as per IS 456:2000(NDT test performed. result found satisfactory)
22 20097927 KHASMAU & BRAMANPUR 20097927/01 No No No No No No Yes No No No No No No Resolved Without using 10mm of aggregate 1st lift casting work done of cylindrical wall of OHT. 10mm aggregate not available at site during casting.(performed NDT test ( Report number-RTHPL/2025/6391)
23 20100818 YOHAN 20100818/01 No No Yes No No No No No No No No No No Resolved As per IS Code- 456:2000, the result of cube samples of 28 days were found to be unsatisfactory. TKC is instructed to do the needful to ascertain the quality of Over Head Tank, so that quality of the same can be maintained.(IIT BHU letter no. CE/PRM/2025-26/1517 DATED-08.07.2025 report result found satisfactory.)
24 20043845 Kalana 20043845/01 No Yes No No No No No No Yes No No Yes No Resolved Resolved Resolved It has been observed that during site visit column above Ground brace beam of OHT not in proper alignment.( Dismantling has been done)
25 20099435 PAHARPUR 20099435/01 No Yes No No No No No No No No No No No Resolved 4th lift column of OHT has not been done in proper alignment (dismantling has been done.)
26 20079117 KEWAI 20079117/01 No No No No No No No No No No No No No
27 20068375 KESURWA 20068375/01 No No No Yes No No No No No No No No No Resolved Steel bar has been exposed after casting and also it has been observed that honeycomb has been found in 1st brace beam of OHT at site.which is not acceptable as per IS code 456:(2000)clause- 13.3.1(NDT test conducted on dated 16.08.2025. found satisfactory)
28 20075544 BAGBADSHAHI 20075544/01 No No No No No No Yes No No No No No No Resolved Concrete work of raft foundation of OHT starts without material testing(Material test performed found ok)
29 20089220 DANDA AMAULI 20089220/01 No No No Yes No No No No No No No No No Resolved steel bar has been exposed at the junction of beam and column. OHT does not look in plumb.
30 20089230 SARAKANDI 20089230/01 No No No No Yes No No No No No No No No Resolved Bottom dowel bar of OHT staircase at plinth level has been cut. It is difficult to provided steel bar with proper development length. Take corrective action regarding this issue.(rectified with help of electric welding)
31 20095164 ALLIPUR 20095164/01 No No No No No No Yes No No No No No No Resolved Rusted sheet is used in shuttering of bottom slab of OHT. Shuttering oil has not applied over the sheet.(reinforcement is replaced)
32 20095789 KISHUNPUR KAPILI 20095789/01 No No No No No No Yes No No No No No No Resolved After binding of steel bars the work has been stopped for long time and due to which trench of OHT filled with water. Steel bars have been rusted and also settlement of soil may be occurred.(re inforcement to be replaced )
33 20097495 ALAMPUR GAURIYA 20097495/01 No No No No No No Yes No No No No No No Resolved Rusted steel bars have been used for the reinforcement of bottom dome of OHT. And also shuttering plate has been observed rusted, Shuttering oil was not applied.(reinforcement replaced)
34 20097544 RAIPUR BHASRAULI 20097544/01 No No No No No No Yes No No No No No No Resolved Rusted steel bars have been used for the reinforcement of OHT raft.(reinforcement of OHT raft bas been replaced)
35 20097720 AJDUPUR 20097720/01 No No No No No No Yes No No No No No No Resolved Rusted steel bar has been used at site.(reinforcement is replaced)
36 20075493 SAMASPUR 20075493/01 No No No No Yes No No No No No No No No Without reinforcement checking and material testing of raft foundation of OHT casting work done at site.(Recommended for Rebar scanning test)
37 20074573 MUBARAKPUR,GARIYABICHHIYAWAN 20074573/01 No No No No No No Yes No No No No No No Rain water has been accumulated over the foundation of OHT. Water wills seepage inside the foundation and cause excessive settlement.
38 20074518 BHOGALPUR 20074518/01 No No No No No No Yes No No No No No No Water logging over OHT foundation(SBC test pending)
39 20079059 MAWAIYA GUNEER GRAM PANCHAYAT WATER SUPPLY SCHEME 20079059/01 No Yes No No No No No No Yes No No Yes No Horizontal alignment of beams of OHT have not been found properly at site.(Instruction given to change pre cast elements)
40 20081170 MOHMMDIPUR 20081170/01 No Yes No No No No No No Yes No No Yes No Column above second brace beam was not found in proper vertical alignment.(Instruction given to TKC to dismantle)
41 20067828 DEVGAON 20067828/01 No No No No Yes No No No No No No No No Many numbers of steel bars of column of OHT has been cut down at plinth level . It is difficult to provide steel bars with proper development length . Take corrective action regarding this .(Recommended dismantling/ Rebaring of steel/ coupling of steel bar.)
42 20099434 BARAGAON 20099434/01 No No No No No No Yes No No No No No No Steel bars have been found severely rusted which was left for column above raft.(recommended for reinforcement to be replace)
43 20067823 BAIJANI 20067823/01 No No No Yes Yes No No No No No No No No Resolved 1.Due to clear cover not maintained, steel has clear visible in first flight staircase of OHT after casting. (dismantling has been done.) 2.Casting of Top dome was done without steel checking. RFI was not raised .(recommended for rebar scanning)
44 20074569 BARKATPUR 20074569/01 No No No No No No Yes No No No No No No Construction work on the OHT has been halted by TKC for over six months following the concreting of its raft foundation; consequently, waterlogging has caused a layer of sand to accumulate over the structure, which could lead to the corrosion of the steel bars used in the OHT.
45 20081191 CHHEWKA 20081191/01 Yes No No No No No No No No No No No No Resolved It has been observed that honeycomb has been found in 3rd brace beam of OHT at site.(NDT test has been done)
46 20097520 KISHUNPUR 20097520/01 No No No No Yes No No No No No No No No Resolved It has been observed that the distribution bars of conical wall and bottom dome of OHT have not been found as per approved drawing.(Rebar scanning and NDT test has been done)
47 20062954 BARAI KHURD 20062954/01 No No No No Yes No No No No No No No No Steel bars of OHT staircase at plinth level have been cut. It is difficult to provide steel bars with proper development length. Its suggested to TKC representative kindly take corrective action.(Recommended Rebaring of steel/ coupling of steel bar.)
48 20078977 SAMRAHA, ABDULLAPUR WAKER 20078977/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond.
49 20089315 AJAMPUR GADWA 20089315/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
50 20043887 Badahar 20043887/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond.
51 20067816 BANARSHI 20067816/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
52 20085893 BASAWAN KHERA 20085893/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the canal
53 20078984 BERUAI &JAMALAMAW 20078984/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the canal
54 20078862 Chaimalpur 20078862/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the canal
55 20092339 CHANDPUR 20092339/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
56 20044149 Chhichha 20044149/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
57 20097510 DASAULI 20097510/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
58 20106717 DATTAULI GRAM PANCHAYAT WATER SUPPLY SCHEME 20106717/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
59 20102035 DHARMGADPUR 20102035/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
60 20061332 DULAPUR 20061332/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
61 20097459 GEDURI 20097459/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
62 20100806 GHANGHAOL 20100806/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the canal
63 20089212 GAURA 20089212/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
64 20079055 HAFIJPUR HARKARAN 20079055/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
65 20079120 HASANAPUR 20079120/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
66 20079086 HIMMATPUR AND UMARKOLA KHURMA NAGAR 20079086/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the canal
67 20079084 ITRORA PILKHINI Gram Panchayat Water Supply Schem 20079084/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the canal
68 20043844 Janta 20043844/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
69 20097517 KANDHIYA 20097517/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
70 20089931 KHAIRABAD 20089931/01 No No No No No No No No No No No No Yes Approximately 80 meters away from the pond
71 20068406 KHATAULI, KORARI 20068406/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
72 20066466 KORWAN 20066466/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
73 20085872 LAKHANKHEDA 20085872/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
74 20100787 LALAULI 20100787/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
75 20079124 MADURI 20079124/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
76 20043847 Malwan 20043847/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond & canal
77 20079037 MAMREJPUR&REWARI KHURD 20079037/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
78 20061493 MAWAI 20061493/01 No No No No No No No No No No No No Yes Approximately 80 meters away from the canal
79 20043849 Missi 20043849/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
80 20079069 NAMA MAU GRAM PANCHAYAT WATER SUPPLY SCHEME 20079069/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
81 20079145 PAHUR & RAMPUR GRAM PANCHAYAT WATER SUPPLY SCHEME 20079145/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
82 20079142 PRATAPPUR GRAM PANCHAYAT WATER SUPPLY SCHEME 20079142/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
83 20061443 RAHMAT DAULATPUR 20061443/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
84 20079073 RANA 20079073/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
85 20097478 RASULPUR URF VAISAPUR 20097478/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
86 20044317 Sardarpur 20044317/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
87 20102045 SARKANDI 20102045/02 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond & canal
88 20061503 SAMOURA 20061503/01 No No No No No No No No No No No No Yes Approximately 60 meters away from the canal
89 20097910 SONHI 20097910/01 No No No No No No No No No No No No Yes Approximately 30 meters away from the pond
90 20061317 Suswan Bujurg Gram Panchayat Water Supply Scheme 20061317/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the pond
91 20097916 TEKSARI BUJURG 20097916/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
92 20100795 URAULI 20100795/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
93 20097538 VIJAYEPUR 20097538/01 No No No No No No No No No No No No Yes Approximately 100 meters away from the canal
94 20089936 DHARAUTALALPUR 2. KHURMABAD 20089936/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
95 20095778 DEVLAN 20095778/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
96 20092360 Gopalpur & Hasanapur 20092360/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
97 20097525 RAMNAGAR KAUHAN 20097525/01 No No No No No No No No No No No No Yes Approximately 50 meters away from the pond
98 20075525 DEVMAI 20075525/01 No Yes No No Yes No No No Yes No No No No Resolved Resolved Resolved Dismantling work for all columns has been completed.
99 20067827 KURUSTI KALA 20067827/01 No No No No Yes No No No No No No No No Steel bars of column have been found cut at the face of column. Steel bar should be left of development length size at the face of column. Dismantle the column and splice the bars as per drawing.(Dismantle the column and splice the bars as per drawing.)
100 20097251 SHIVARI 20097251/01 No No No No No No Yes No Yes No No Yes No Resolved Resolved Resolved Crack has been observed in junction point of raft footing and three way column of OHT.(Instruction given to TKC to replace of pre cast elements)
101 20079137 BHIKAMPUR AND TENDULI LAKHIPUR GP 20079137/01 No No No No No Yes No No No No No No No Resolved Anchor fastener of ZA tank has been exposed after installation due to slab broken by Hilti machine. During water loading condition ZA tank may collapse due to this negligence.(zinc part (Fastener) to be replaced)
102 20079007 IRADATPUR CHATURBHUJPUR 20079007/01 No Yes No No No No No No Yes No No Yes No Resolved Resolved Resolved As per visual inspection it has come to our notice that the Verticality of Over Head Tank does not look in plumb.