| 1 |
Raebareli |
7201390 |
ITAURA BUJURG PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
794.36 |
671.30 |
671.30 |
0.00 |
123.06 |
794.36 |
Under Construction |
95.00 |
"1. OHT work alloted to M/S Bandhu Enterprises in year 2020 but he not completed OHT.
2. Agreement terminated , New tender called vide NIT No. 2327/M-7/53 Dated 07/10/2026. tentative time for completion is march 2027."
|
| 2 |
Raebareli |
20084310 |
RAMKHERA GROUP OF VILLEGAES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
666.70 |
34.15 |
34.15 |
0.00 |
632.55 |
666.70 |
Under Construction |
67.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 14.000 km pipeline completed out of 22.428 km
3. OHT: 2 Nos OHT WIP out of 02 nos OHT
4. Progress: Overall Physical progress 67.0% vs financial progress 5.12%.
5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."
|
| 3 |
Raebareli |
20084337 |
NERTHUWA GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1922.61 |
291.35 |
291.35 |
0.00 |
1631.26 |
1922.61 |
Under Construction |
57.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 78.100 km pipeline completed out of 82.615 km
3. OHT: 3 Nos OHT WIP, 03 Nos OHT not started out of 06 nos OHT
4. Progress: Overall Physical progress 57.0% vs financial progress 15.15%.
5. Administrative Action: Warning letter issued vide Letter No. 1498 / W-11 / 48 dated 14/07/2026."
|
| 4 |
Raebareli |
20084389 |
MIRAZAPUR AIHARI G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1335.05 |
306.25 |
306.25 |
0.00 |
1028.80 |
1335.05 |
Under Construction |
74.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 69.500 km pipeline completed out of 70.387 km
3. OHT: 4 Nos OHT WIP out of 04 nos OHT
4. Progress: Overall Physical progress 74.0% vs financial progress 22.94%.
5. Administrative Action: Warning letter issued vide Letter No. 1500 / W-11 / 50 dated 14/07/2026."
|
| 5 |
Raebareli |
20084402 |
Ambara Paschim G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
2077.32 |
355.95 |
355.95 |
0.00 |
1721.37 |
2077.32 |
Under Construction |
57.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 95.053 km pipeline completed out of 153.139 km
3. OHT: 5 Nos OHT WIP out of 05 nos OHT
4. Progress: Overall Physical progress 57.0% vs financial progress 17.14%.
5. Administrative Action: Warning letter issued vide Letter No. 1499 / W-11 / 49 dated 14/07/2026."
|
| 6 |
Raebareli |
20084435 |
Neemtikar Group of Villages |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1596.90 |
217.62 |
217.62 |
0.00 |
1379.28 |
1596.90 |
Under Construction |
58.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 52.500 km pipeline completed out of 67.374 km
3. OHT: 2 Nos OHT WIP, 01 Nos OHT not started out of 03 nos OHT
4. Progress: Overall Physical progress 58.0% vs financial progress 13.63%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1669 / W-11 / 64 dated 29/07/2026."
|
| 7 |
Raebareli |
20084452 |
Govindpur G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1621.23 |
720.43 |
720.43 |
0.00 |
900.80 |
1621.23 |
Under Construction |
73.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 79.610 km pipeline completed out of 79.136 km
3. OHT: 3 Nos OHT WIP, 4 Nos OHT completed out of 07 nos OHT
4. Progress: Overall Physical progress 73.0% vs financial progress 44.44%.
"
|
| 8 |
Raebareli |
20084527 |
THULANDI Water Supply |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1575.16 |
144.23 |
144.23 |
0.00 |
1430.93 |
1575.16 |
Under Construction |
56.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 26.500 km pipeline completed out of 55.991 km
3. OHT:03 Nos OHT not started out of 03 nos OHT
4. Progress: Overall Physical progress 56.0% vs financial progress 9.16%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1668 / W-11 / 63 dated 29/07/2026.
6. Penalty: 1% Liquidated Damag |
| 9 |
Raebareli |
20084571 |
SEHGON PASHCHIM Water Supply |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
784.18 |
151.18 |
151.18 |
0.00 |
633.00 |
784.18 |
Under Construction |
67.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 33.500 km pipeline completed out of 35.419 km
3. OHT: 1 Nos OHT WIP, 01 Nos OHT not started out of 02 nos OHT
4. Progress: Overall Physical progress 67.0% vs financial progress 19.28%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1669 / W-11 / 64 dated 29/07/2026."
|
| 10 |
Raebareli |
20085243 |
PAKHRAULI GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
953.40 |
214.52 |
214.52 |
0.00 |
738.88 |
953.40 |
Under Construction |
78.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 39.000 km pipeline completed out of 37.513 km
3. OHT: 2 Nos OHT WIP out of 02 nos OHT
4. Progress: Overall Physical progress 78.0% vs financial progress 22.50%.
5. Administrative Action: Warning letter issued vide Letter No. 1489 / W-11 / 39 dated 14/07/2026."
|
| 11 |
Raebareli |
20085429 |
BEHATA KALAN GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1701.01 |
337.26 |
337.26 |
0.00 |
1363.75 |
1701.01 |
Under Construction |
81.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 78.000 km pipeline completed out of 73.980 km
3. OHT: 2 Nos OHT completed out of 02 nos OHT
4. Progress: Overall Physical progress 81.0% vs financial progress 19.83%.
5. Administrative Action: Warning letter issued vide Letter No. 1495 / W-11 / 45 dated 14/07/2026."
|
| 12 |
Raebareli |
20085447 |
BALA GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1577.47 |
109.72 |
109.72 |
0.00 |
1467.75 |
1577.47 |
Under Construction |
58.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 25.000 km pipeline completed out of 49.169 km
3. OHT: 1 Nos OHT WIP, 01 Nos OHT not started out of 02 nos OHT
4. Progress: Overall Physical progress 58.0% vs financial progress 6.96%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1668 / W-11 / 63 dated 29/07/2026.
6. Penalty: 1% |
| 13 |
Raebareli |
20085473 |
KAMALPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
952.96 |
145.57 |
145.57 |
0.00 |
807.39 |
952.96 |
Under Construction |
83.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 48.500 km pipeline completed out of 52.594 km
3. OHT: 1 Nos OHT WIP out of 01 nos OHT
4. Progress: Overall Physical progress 83.0% vs financial progress 15.28%.
5. Administrative Action: Warning letter issued vide Letter No. 1500 / W-11 / 50 dated 14/07/2026."
|
| 14 |
Raebareli |
20085495 |
Pahuri G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
746.78 |
155.04 |
155.04 |
0.00 |
591.74 |
746.78 |
Under Construction |
52.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 36.862 km pipeline completed out of 50.475 km
3. OHT: 1 Nos OHT WIP out of 01 nos OHT
4. Progress: Overall Physical progress 52.0% vs financial progress 20.76%.
5. Administrative Action: Warning letter issued vide Letter No. 1499 / W-11 / 49 dated 14/07/2026."
|
| 15 |
Raebareli |
20085544 |
AIHAR GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
2004.50 |
180.84 |
180.84 |
0.00 |
1823.66 |
2004.50 |
Under Construction |
61.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 42.000 km pipeline completed out of 54.610 km
3. OHT: 3 Nos OHT WIP, 03 Nos OHT not started out of 06 nos OHT
4. Progress: Overall Physical progress 61.0% vs financial progress 9.02%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1667 / W-11 / 62 dated 29/07/2026.
6. Penalty: 1% |
| 16 |
Raebareli |
20085566 |
MAJHIGAWAN G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1140.00 |
72.12 |
72.12 |
0.00 |
1067.88 |
1140.00 |
Under Construction |
53.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 36.000 km pipeline completed out of 62.970 km
3. OHT: 1 Nos OHT WIP,01 Nos OHT not started out of 02 nos OHT
4. Progress: Overall Physical progress 53.0% vs financial progress 6.33%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1667 / W-11 / 62 dated 29/07/2026.
6. Penalty: 1% L |
| 17 |
Raebareli |
20085622 |
PASCHIM GAON GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
980.70 |
277.15 |
277.15 |
0.00 |
703.55 |
980.70 |
Under Construction |
72.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 35.000 km pipeline completed out of 41.020 km
3. OHT: 1 Nos OHT completed out of 01 nos OHT
4. Progress: Overall Physical progress 72.0% vs financial progress 28.26%.
5. Administrative Action: Warning letter issued vide Letter No. 1495 / W-11 / 45 dated 14/07/2026."
|
| 18 |
Raebareli |
20085997 |
BARAMJITPUR URF KHWATA G.O.V. |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
959.00 |
57.34 |
57.34 |
0.00 |
901.66 |
959.00 |
Under Construction |
58.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 33.000 km pipeline completed out of 41.487 km
3. OHT: 01 Nos OHT not started out of 01 nos OHT
4. Progress: Overall Physical progress 58.0% vs financial progress 5.98%.
5. Administrative Action: Warning letter issued vide Letter No. 1489 / W-11 / 39 dated 14/07/2026."
|
| 19 |
Raebareli |
20086021 |
Ichauli Water Supply |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1065.37 |
185.84 |
185.84 |
0.00 |
879.53 |
1065.37 |
Under Construction |
65.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 46.900 km pipeline completed out of 50.385 km
3. OHT: 1 Nos OHT WIP out of 01 nos OHT
4. Progress: Overall Physical progress 65.0% vs financial progress 17.44%.
5. Administrative Action: Warning letter issued vide Letter No. 1498 / W-11 / 48 dated 14/07/2026."
|
| 20 |
Raebareli |
20086029 |
RAGHOPUR Water Supply |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
740.17 |
67.10 |
67.10 |
0.00 |
673.07 |
740.17 |
Under Construction |
68.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 20.000 km pipeline completed out of 31.290 km
3. OHT: 1 Nos OHT WIP out of 01 nos OHT
4. Progress: Overall Physical progress 68.0% vs financial progress 9.07%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1669 / W-11 / 64 dated 29/07/2026."
|
| 21 |
Raebareli |
20086068 |
JOHWAHISAR GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1522.06 |
121.21 |
121.21 |
0.00 |
1400.85 |
1522.06 |
Under Construction |
53.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 53.510 km pipeline completed out of 63.000 km
3. OHT: 4 Nos OHT WIP, 02 Nos OHT not started out of 06 nos OHT
4. Progress: Overall Physical progress 53.0% vs financial progress 7.96%.
5. Administrative Action: Warning letter issued vide Letter No. 1496 / W-11 / 46 dated 14/07/2026."
|
| 22 |
Raebareli |
20086102 |
Meethapur G.O.V water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
261.37 |
50.95 |
50.95 |
0.00 |
210.42 |
261.37 |
Under Construction |
53.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 14.330 km pipeline completed out of 18.613 km
3. OHT: Existing OHT Repairing work WIP (No new OHT proposed)
4. Progress: Overall Physical progress 53.0% vs financial progress 19.49%.
5. Administrative Action: Warning letter issued vide Letter No. 1499 / W-11 / 49 dated 14/07/2026."
|
| 23 |
Raebareli |
20086123 |
SB Kheda G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
502.01 |
55.94 |
55.94 |
0.00 |
446.07 |
502.01 |
Under Construction |
55.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 17.250 km pipeline completed out of 27.879 km
3. OHT: 2 Nos OHT WIP out of 02 nos OHT
4. Progress: Overall Physical progress 55.0% vs financial progress 11.14%.
5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."
|
| 24 |
Raebareli |
20086508 |
KAND RAWAN G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3160.70 |
171.46 |
171.46 |
0.00 |
2989.24 |
3160.70 |
Under Construction |
52.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 106.500 km pipeline completed out of 145.181 km
3. OHT: 07 Nos OHT not started out of 07 nos OHT
4. Progress: Overall Physical progress 52.0% vs financial progress 5.42%.
5. Administrative Action: Warning letter issued vide Letter No. 1501 / W-11 / 51 dated 14/07/2026 and final notice issued vide Letter No. 1670 / W-11 / 65 dated 29/07/2026.
6. Penalty: 1% Liquidated Da |
| 25 |
Raebareli |
20086519 |
LODIPUR UTRAUWA GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
2346.99 |
256.39 |
256.39 |
0.00 |
2090.60 |
2346.99 |
Under Construction |
58.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 74.934 km pipeline completed out of 89.900 km
3. OHT: 1 Nos OHT WIP, 07 Nos OHT not started out of 08 nos OHT
4. Progress: Overall Physical progress 58.0% vs financial progress 10.92%.
5. Administrative Action: Warning letter issued vide Letter No. 1497 / W-11 / 47 dated 14/07/2026 and final notice issued vide Letter No. 1663 / W-11 / 58 dated 29/07/2026.
6. Penalty: 1% |
| 26 |
Raebareli |
20086638 |
BHAON GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3679.68 |
921.65 |
921.65 |
0.00 |
2758.03 |
3679.68 |
Under Construction |
58.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 105.000 km pipeline completed out of 138.100 km
3. OHT: 5 Nos OHT WIP, 03 Nos OHT not started out of 08 nos OHT
4. Progress: Overall Physical progress 58.0% vs financial progress 25.05%.
5. Administrative Action: Warning letter issued vide Letter No. 1491 / W-11 / 41 dated 14/07/2026 and final notice issued vide Letter No. 1666 / W-11 / 61 dated 29/07/2026.
6. Penalty: |
| 27 |
Raebareli |
20086653 |
MON WATER SUPPLY |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3603.60 |
611.66 |
611.66 |
0.00 |
2991.94 |
3603.60 |
Under Construction |
54.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 96.756 km pipeline completed out of 154.576 km
3. OHT: 7 Nos OHT WIP, 02 Nos OHT not started out of 09 nos OHT
4. Progress: Overall Physical progress 54.0% vs financial progress 16.97%.
5. Administrative Action: Warning letter issued vide Letter No. 1497 / W-11 / 47 dated 14/07/2026 and final notice issued vide Letter No. 1664 / W-11 / 59 dated 29/07/2026.
6. Penalty: 1 |
| 28 |
Raebareli |
20086676 |
GHURWARA GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
2296.30 |
471.80 |
471.80 |
0.00 |
1824.50 |
2296.30 |
Under Construction |
69.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 103.000 km pipeline completed out of 115.000 km
3. OHT: 3 Nos OHT WIP, 2 Nos OHT completed and 03 Nos OHT not started out of 08 nos OHT
4. Progress: Overall Physical progress 69.0% vs financial progress 20.55%.
5. Administrative Action: Warning letter issued vide Letter No. 1490 / W-11 / 40 dated 14/07/2026."
|
| 29 |
Raebareli |
20086724 |
BHojpur G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3616.33 |
419.09 |
419.09 |
0.00 |
3197.24 |
3616.33 |
Under Construction |
87.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 140.580 km pipeline completed out of 140.000 km
3. OHT: 11 Nos OHT WIP, 01 Nos OHT not started out of 12 nos OHT
4. Progress: Overall Physical progress 87.0% vs financial progress 11.59%.
5. Administrative Action: Warning letter issued vide Letter No. 1492 / W-11 / 42 dated 14/07/2026."
|
| 30 |
Raebareli |
20086769 |
Bannamau G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
2826.62 |
362.36 |
362.36 |
0.00 |
2464.26 |
2826.62 |
Under Construction |
54.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 88.000 km pipeline completed out of 96.000 km
3. OHT: 7 Nos OHT WIP, 03 Nos OHT not started out of 10 nos OHT
4. Progress: Overall Physical progress 54.0% vs financial progress 12.82%.
5. Administrative Action: Warning letter issued vide Letter No. 1493 / W-11 / 43 dated 14/07/2026."
|
| 31 |
Raebareli |
20094863 |
HARCHANDPUR GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1158.50 |
61.06 |
61.06 |
0.00 |
1097.44 |
1158.50 |
Under Construction |
61.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 39.490 km pipeline completed out of 42.000 km
3. OHT: 2 Nos OHT WIP, 02 Nos OHT not started out of 04 nos OHT
4. Progress: Overall Physical progress 61.0% vs financial progress 5.27%.
5. Administrative Action: Warning letter issued vide Letter No. 1496 / W-11 / 46 dated 14/07/2026."
|
| 32 |
Raebareli |
20095086 |
FIROJPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
612.00 |
35.66 |
35.66 |
0.00 |
576.34 |
612.00 |
Under Construction |
52.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 21.000 km pipeline completed out of 31.700 km
3. OHT: 1 Nos OHT WIP, 01 Nos OHT not started out of 02 nos OHT
4. Progress: Overall Physical progress 52.0% vs financial progress 5.83%.
5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."
|
| 33 |
Raebareli |
20095091 |
Jagatpur retrofitting water supply scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
234.22 |
58.78 |
58.78 |
0.00 |
175.44 |
234.22 |
Under Construction |
56.00 |
"1. Distribution: 5.04 KM pipeline completed out of 17.32 KM (Old Retrofit scheme)
2. TW: 01 no. tw completed out of 1 nos. tw.
3.Remaining work WIP."
|
| 34 |
Raebareli |
20095094 |
DEEH (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3529.83 |
815.09 |
815.09 |
0.00 |
2714.74 |
3529.83 |
Under Construction |
57.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 110.000 km pipeline completed out of 135.900 km
3. OHT: 4 Nos OHT WIP,03 Nos OHT not started out of 07 nos OHT
4. Progress: Overall Physical progress 57.0% vs financial progress 23.09%.
5. Administrative Action: Warning letter issued vide Letter No. 1491 / W-11 / 41 dated 14/07/2026 and final notice issued vide Letter No. 1665 / W-11 / 60 dated 29/07/2026.
6. Penalty: 1 |
| 35 |
Raebareli |
20095120 |
ASRAFPUR (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1909.90 |
234.57 |
234.57 |
0.00 |
1675.33 |
1909.90 |
Under Construction |
54.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 50.320 km pipeline completed out of 76.100 km
3. OHT: 5 Nos OHT WIP, 01 Nos OHT not started out of 06 nos OHT
4. Progress: Overall Physical progress 54.0% vs financial progress 12.28%.
5. Administrative Action: Warning letter issued vide Letter No. 1499 / W-11 / 49 dated 14/07/2026.
6. Penalty: 1% Liquidated Damages (LD) recommended vide Letter No. 1855 / W-11 / 70 date |
| 36 |
Raebareli |
20095128 |
KUNWAR MAU (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1016.91 |
66.75 |
66.75 |
0.00 |
950.16 |
1016.91 |
Under Construction |
57.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 22.000 km pipeline completed out of 55.908 km
3. OHT: 03 Nos OHT not started out of 03 nos OHT
4. Progress: Overall Physical progress 57.0% vs financial progress 6.56%.
5. Administrative Action: Warning letter issued vide Letter No. 1497 / W-11 / 47 dated 14/07/2026 and final notice issued vide Letter No. 1662 / W-11 / 57 dated 29/07/2026.
6. Penalty: 1% Liquidated Dama |
| 37 |
Raebareli |
20095374 |
SANDAHA (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
648.09 |
206.19 |
206.19 |
0.00 |
441.90 |
648.09 |
Under Construction |
53.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 34.000 km pipeline completed out of 34.939 km
3. OHT: 01 Nos OHT not started out of 01 nos OHT
4. Progress: Overall Physical progress 53.0% vs financial progress 31.82%.
5. Administrative Action: Warning letter issued vide Letter No. 1500 / W-11 / 50 dated 14/07/2026."
|
| 38 |
Raebareli |
20095377 |
NINAWAN (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
882.16 |
117.99 |
117.99 |
0.00 |
764.17 |
882.16 |
Under Construction |
53.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 36.20 km pipeline completed out of 61.673 km
3. OHT: 1 Nos OHT WIP, 0 Nos OHT completed out of 02 nos OHT
4. Progress: Overall Physical progress 53.0% vs financial progress 13.38%.
5. Administrative Action: Warning letter issued vide Letter No. 1499 / W-11 / 49 dated 14/07/2026.
6. Penalty: 1% Liquidated Damages (LD) recommended vide Letter No. 1855 / W-11 / 70 dated 14 |
| 39 |
Raebareli |
20095382 |
Ralpur G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1480.00 |
659.97 |
659.97 |
0.00 |
820.03 |
1480.00 |
Under Construction |
81.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 74.390 km pipeline completed out of 86.864 km
3. OHT: 4 Nos OHT WIP, 2 Nos OHT completed out of 06 nos OHT
4. Progress: Overall Physical progress 81.0% vs financial progress 44.59%.
"
|
| 40 |
Raebareli |
20095385 |
Sareni G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1296.10 |
140.02 |
140.02 |
0.00 |
1156.08 |
1296.10 |
Under Construction |
87.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 59.750 km pipeline completed out of 60.293 km
3. OHT: 4 Nos OHT WIP out of 04 nos OHT
4. Progress: Overall Physical progress 87.0% vs financial progress 10.80%.
5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."
|
| 41 |
Raebareli |
20095392 |
ASHA RASIDPUR (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1926.67 |
123.95 |
123.95 |
0.00 |
1802.72 |
1926.67 |
Under Construction |
54.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 31.000 km pipeline completed out of 87.616 km
3. OHT: 06 Nos OHT not started out of 06 nos OHT
4. Progress: Overall Physical progress 54.0% vs financial progress 6.43%.
5. Administrative Action: Warning letter issued vide Letter No. 1497 / W-11 / 47 dated 14/07/2026 and final notice issued vide Letter No. 1662 / W-11 / 57 dated 29/07/2026.
6. Penalty: 1% Liquidated Dama |