| 1 |
Raebareli |
7201390 |
ITAURA BUJURG PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
794.36 |
671.30 |
671.30 |
0.00 |
123.06 |
794.36 |
Under Construction |
95.00 |
"1. OHT work alloted to M/S Bandhu Enterprises in year 2020 but he not completed OHT.
2. Agreement terminated , New tender called vide NIT No. 2327/M-7/53 Dated 07/10/2026. tentative time for completion is march 2027."
|
| 2 |
Raebareli |
20085243 |
PAKHRAULI GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
953.40 |
214.52 |
214.52 |
0.00 |
738.88 |
953.40 |
Under Construction |
78.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 39.000 km pipeline completed out of 37.513 km
3. OHT: 2 Nos OHT WIP out of 02 nos OHT
4. Progress: Overall Physical progress 78.0% vs financial progress 22.50%.
5. Administrative Action: Warning letter issued vide Letter No. 1489 / W-11 / 39 dated 14/07/2026."
|
| 3 |
Raebareli |
20085429 |
BEHATA KALAN GROUP OF VILLAGES |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1701.01 |
337.26 |
337.26 |
0.00 |
1363.75 |
1701.01 |
Under Construction |
81.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 78.000 km pipeline completed out of 73.980 km
3. OHT: 2 Nos OHT completed out of 02 nos OHT
4. Progress: Overall Physical progress 81.0% vs financial progress 19.83%.
5. Administrative Action: Warning letter issued vide Letter No. 1495 / W-11 / 45 dated 14/07/2026."
|
| 4 |
Raebareli |
20085473 |
KAMALPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
952.96 |
145.57 |
145.57 |
0.00 |
807.39 |
952.96 |
Under Construction |
83.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 48.500 km pipeline completed out of 52.594 km
3. OHT: 1 Nos OHT WIP out of 01 nos OHT
4. Progress: Overall Physical progress 83.0% vs financial progress 15.28%.
5. Administrative Action: Warning letter issued vide Letter No. 1500 / W-11 / 50 dated 14/07/2026."
|
| 5 |
Raebareli |
20086724 |
BHojpur G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
3616.33 |
419.09 |
419.09 |
0.00 |
3197.24 |
3616.33 |
Under Construction |
87.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 140.580 km pipeline completed out of 140.000 km
3. OHT: 11 Nos OHT WIP, 01 Nos OHT not started out of 12 nos OHT
4. Progress: Overall Physical progress 87.0% vs financial progress 11.59%.
5. Administrative Action: Warning letter issued vide Letter No. 1492 / W-11 / 42 dated 14/07/2026."
|
| 6 |
Raebareli |
20095382 |
Ralpur G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1480.00 |
659.97 |
659.97 |
0.00 |
820.03 |
1480.00 |
Under Construction |
81.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 74.390 km pipeline completed out of 86.864 km
3. OHT: 4 Nos OHT WIP, 2 Nos OHT completed out of 06 nos OHT
4. Progress: Overall Physical progress 81.0% vs financial progress 44.59%.
"
|
| 7 |
Raebareli |
20095385 |
Sareni G.O.V Reorganisational water Supply Scheme (Solar) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1296.10 |
140.02 |
140.02 |
0.00 |
1156.08 |
1296.10 |
Under Construction |
87.00 |
"1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned.
2. Distribution: 59.750 km pipeline completed out of 60.293 km
3. OHT: 4 Nos OHT WIP out of 04 nos OHT
4. Progress: Overall Physical progress 87.0% vs financial progress 10.80%.
5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."
|