S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Raebareli 7201390 ITAURA BUJURG PWS NRDWP Jal Nigam YES NO NO 794.36 671.30 671.30 0.00 123.06 794.36 Under Construction 95.00 "1. OHT work alloted to M/S Bandhu Enterprises in year 2020 but he not completed OHT. 2. Agreement terminated , New tender called vide NIT No. 2327/M-7/53 Dated 07/10/2026. tentative time for completion is march 2027."
2 Raebareli 20085243 PAKHRAULI GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 953.40 214.52 214.52 0.00 738.88 953.40 Under Construction 78.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 39.000 km pipeline completed out of 37.513 km 3. OHT: 2 Nos OHT WIP out of 02 nos OHT 4. Progress: Overall Physical progress 78.0% vs financial progress 22.50%. 5. Administrative Action: Warning letter issued vide Letter No. 1489 / W-11 / 39 dated 14/07/2026."
3 Raebareli 20085429 BEHATA KALAN GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1701.01 337.26 337.26 0.00 1363.75 1701.01 Under Construction 81.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 78.000 km pipeline completed out of 73.980 km 3. OHT: 2 Nos OHT completed out of 02 nos OHT 4. Progress: Overall Physical progress 81.0% vs financial progress 19.83%. 5. Administrative Action: Warning letter issued vide Letter No. 1495 / W-11 / 45 dated 14/07/2026."
4 Raebareli 20085473 KAMALPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 952.96 145.57 145.57 0.00 807.39 952.96 Under Construction 83.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 48.500 km pipeline completed out of 52.594 km 3. OHT: 1 Nos OHT WIP out of 01 nos OHT 4. Progress: Overall Physical progress 83.0% vs financial progress 15.28%. 5. Administrative Action: Warning letter issued vide Letter No. 1500 / W-11 / 50 dated 14/07/2026."
5 Raebareli 20086724 BHojpur G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 3616.33 419.09 419.09 0.00 3197.24 3616.33 Under Construction 87.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 140.580 km pipeline completed out of 140.000 km 3. OHT: 11 Nos OHT WIP, 01 Nos OHT not started out of 12 nos OHT 4. Progress: Overall Physical progress 87.0% vs financial progress 11.59%. 5. Administrative Action: Warning letter issued vide Letter No. 1492 / W-11 / 42 dated 14/07/2026."
6 Raebareli 20095382 Ralpur G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 1480.00 659.97 659.97 0.00 820.03 1480.00 Under Construction 81.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 74.390 km pipeline completed out of 86.864 km 3. OHT: 4 Nos OHT WIP, 2 Nos OHT completed out of 06 nos OHT 4. Progress: Overall Physical progress 81.0% vs financial progress 44.59%. "
7 Raebareli 20095385 Sareni G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 1296.10 140.02 140.02 0.00 1156.08 1296.10 Under Construction 87.00 "1. Issue: Due to non-availability of funds from oct 2024. work progress is significantly slower than planned. 2. Distribution: 59.750 km pipeline completed out of 60.293 km 3. OHT: 4 Nos OHT WIP out of 04 nos OHT 4. Progress: Overall Physical progress 87.0% vs financial progress 10.80%. 5. Administrative Action: Warning letter issued vide Letter No. 1502 / W-11 / 52 dated 14/07/2026."