S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Jhansi 8157263 BAMHROULI VILLAGE WATER SUPPLY SCHEME OLD RETROFIT Jal Nigam YES NO NO 304.32 89.11 89.11 0.00 215.21 304.32 Under Construction 71.00 The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including Laying of around 350 m of 63 mm HDPE pipeline, 225 m of 90 mm HDPE pipeline, Interconnection works, approximately 150-200 functional household tap connections, 500 meters of concrete road restoration and structural painting and finishing—is scheduled for completion by the end of October 2026
2 Jhansi 20072943 Karguwan Village Water Supply Scheme OLD RETROFIT Jal Nigam YES NO NO 266.89 65.51 65.51 0.00 201.38 266.89 Under Construction 83.00 The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including approximately 50 functional household tap connections, 50 to 100 meters of concrete road restoration (In Patches due to repair of leakage in pipeline), and structural painting and finishing—is scheduled for completion by the end of October 2026
3 Jhansi 20093452 Ambargarh Retrofitting Water Supply Scheme OLD RETROFIT Jal Nigam YES NO NO 286.97 152.13 152.13 0.00 134.84 286.97 Under Construction 83.00 The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including approximately 85 functional household tap connections, 50 to 100 meters of concrete road restoration (in patches due to pipeline leakage repairs), 250 meters of interlocking road repairs, and structural painting and finishing—is scheduled for completion by the end of October 2026.
4 Jhansi 20100879 Haibatpura G.O.V. W/S Scheme NEW RETROFIT Jal Nigam YES NO NO 347.79 34.19 34.19 0.00 313.60 347.79 Under Construction 66.00 Funding shortages have severely delayed progress on the schemes, as contractor payments have been outstanding for two years. As a result, the remaining work is moving at a sluggish pace. The following balance works are currently pending completion: • Distribution Pipeline: Around 1,500 m • Feeder Main (150 mm dia): 2,100 m • Pipeline Interconnections: Pending at 5–6 locations • Road Restoration: 2,100 m (both Cement Concrete [CC] and interlocking tiles)
5 Jhansi 20101021 Prithvipura Naya Khera G.O.V. W/S Scheme. NEW RETROFIT Jal Nigam YES NO NO 368.35 62.00 62.00 0.00 306.35 368.35 Under Construction 77.00 • Two years of outstanding contractor payments have slowed work to a sluggish pace. • Pending Pipelines: Main feeder main 8.0 km and village distribution interconnection • Interconnections & Mechanical: 5 to 6 pipeline interconnections and the booster pump installation/interconnection. • Connections & Finishing: Around 250 Functional Household Tap Connections (FHTCs) and final structural painting/finishing.
6 Jhansi 20101027 Saiyyar Village W/S Reorganization Scheme NEW RETROFIT Jal Nigam YES NO NO 520.21 109.24 109.24 0.00 410.97 520.21 Under Construction 71.00 • Contractor payments are two years overdue, causing work to progress at a very slow pace. • Pending Pipelines: 3.0 km of main feeder main and 3.0 km of distribution pipeline. • Interconnections & Pumps: Pipeline interconnections at 5–6 locations, alongside booster pump installation and its interconnection. • Connections & Civil: 250 Functional Household Tap Connections (FHTCs) and final painting/finishing work of the structures.
7 Jhansi 20101030 Simrawari Village W/S Reorganization Scheme NEW RETROFIT Jal Nigam YES NO NO 1000.89 338.43 338.43 0.00 662.46 1000.89 Under Construction 71.00 • Payments Delayed: Contractor payments are two years overdue, causing significant delays. Consequently, remaining tasks are being executed at a very slow pace. • Pipeline Works: • Main Feeder Main: 700 m remaining. • Distribution Pipeline: 1.5 km outstanding. • Interconnections: 5 to 6 locations pending. • Other Works: • Booster Pump: Installation and interconnection pending. • FHTCs: 50 tap connections remaining. • Finishing: Structure painting and finishing work is incomplete.