| 1 |
Jhansi |
8157263 |
BAMHROULI VILLAGE WATER SUPPLY SCHEME |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
304.32 |
89.11 |
89.11 |
0.00 |
215.21 |
304.32 |
Under Construction |
71.00 |
The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including Laying of around 350 m of 63 mm HDPE pipeline, 225 m of 90 mm HDPE pipeline, Interconnection works, approximately 150-200 functional household tap connections, 500 meters of concrete road restoration and structural painting and finishing—is scheduled for completion by the end of October 2026 |
| 2 |
Jhansi |
20100879 |
Haibatpura G.O.V. W/S Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
347.79 |
34.19 |
34.19 |
0.00 |
313.60 |
347.79 |
Under Construction |
66.00 |
Funding shortages have severely delayed progress on the schemes, as contractor payments have been outstanding for two years. As a result, the remaining work is moving at a sluggish pace.
The following balance works are currently pending completion:
• Distribution Pipeline: Around 1,500 m
• Feeder Main (150 mm dia): 2,100 m
• Pipeline Interconnections: Pending at 5–6 locations
• Road Restoration: 2,100 m (both Cement Concrete [CC] and interlocking tiles) |
| 3 |
Jhansi |
20101027 |
Saiyyar Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
520.21 |
109.24 |
109.24 |
0.00 |
410.97 |
520.21 |
Under Construction |
71.00 |
• Contractor payments are two years overdue, causing work to progress at a very slow pace.
• Pending Pipelines: 3.0 km of main feeder main and 3.0 km of distribution pipeline.
• Interconnections & Pumps: Pipeline interconnections at 5–6 locations, alongside booster pump installation and its interconnection.
• Connections & Civil: 250 Functional Household Tap Connections (FHTCs) and final painting/finishing work of the structures. |
| 4 |
Jhansi |
20101030 |
Simrawari Village W/S Reorganization Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1000.89 |
338.43 |
338.43 |
0.00 |
662.46 |
1000.89 |
Under Construction |
71.00 |
• Payments Delayed: Contractor payments are two years overdue, causing significant delays. Consequently, remaining tasks are being executed at a very slow pace.
• Pipeline Works:
• Main Feeder Main: 700 m remaining.
• Distribution Pipeline: 1.5 km outstanding.
• Interconnections: 5 to 6 locations pending.
• Other Works:
• Booster Pump: Installation and interconnection pending.
• FHTCs: 50 tap connections remaining.
• Finishing: Structure painting and finishing work is incomplete.
|