| 1 |
Jhansi |
20072943 |
Karguwan Village Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
266.89 |
65.51 |
65.51 |
0.00 |
201.38 |
266.89 |
Under Construction |
83.00 |
The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including approximately 50 functional household tap connections, 50 to 100 meters of concrete road restoration (In Patches due to repair of leakage in pipeline), and structural painting and finishing—is scheduled for completion by the end of October 2026 |
| 2 |
Jhansi |
20093452 |
Ambargarh Retrofitting Water Supply Scheme |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
286.97 |
152.13 |
152.13 |
0.00 |
134.84 |
286.97 |
Under Construction |
83.00 |
The work of scheme is currently in progress, and a partial daily water supply has already been established in the village. All remaining work—including approximately 85 functional household tap connections, 50 to 100 meters of concrete road restoration (in patches due to pipeline leakage repairs), 250 meters of interlocking road repairs, and structural painting and finishing—is scheduled for completion by the end of October 2026. |
| 3 |
Jhansi |
20101021 |
Prithvipura Naya Khera G.O.V. W/S Scheme. |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
368.35 |
62.00 |
62.00 |
0.00 |
306.35 |
368.35 |
Under Construction |
77.00 |
• Two years of outstanding contractor payments have slowed work to a sluggish pace.
• Pending Pipelines: Main feeder main 8.0 km and village distribution interconnection
• Interconnections & Mechanical: 5 to 6 pipeline interconnections and the booster pump installation/interconnection.
• Connections & Finishing: Around 250 Functional Household Tap Connections (FHTCs) and final structural painting/finishing. |