| 1 |
Lalitpur |
20089022 |
PURA KALAN VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
290.00 |
0.00 |
0.00 |
0.00 |
290.00 |
290.00 |
Under Construction |
60.00 |
• The scheme is under new retrofitting work and covers 1 village comprising 22 habitations .
• Work has not yet commenced due to pending payment of ₹50.40 lakh against the scheme.
• The agency has stated that the remaining work will be completed within 60 days of after receiving some funds against pending bills.
• Out of the proposed 17 km distribution pipeline, 9 km has been laid and 8 km remains pending.
• Pipeline testing is pending.
• Against the target of |
| 2 |
Lalitpur |
20094881 |
MATHURADANG GOV WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
955.24 |
114.66 |
114.66 |
0.00 |
840.58 |
955.24 |
Under Construction |
60.00 |
• The scheme is under new retrofitting and is operated by Jal Sansthan.
• The plant is currently operational and covers 24 villages, out of which 19 villages are presently receiving water supply.
• pending payment of ₹73.25 lakh against the scheme.
• The agency has stated that the remaining work will be completed within approximately 1.5 months after receiving some funds against pending bills
• Approximately 8 km of distribution pipeline laying is pending.
• Against the target of 8,000 FH |
| 3 |
Lalitpur |
20094959 |
BAR REORGNAIZATION WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
923.00 |
407.82 |
407.82 |
0.00 |
515.18 |
923.00 |
Under Construction |
70.00 |
"• The scheme is under new retrofitting and is operated by Jal Sansthan.
• The agency has stated that the remaining work will be completed within one month after receiving some funds against pending bills .
• Work has not yet commenced due to pending payment of ₹88.62 lakh against the scheme.
• The scheme is currently partially functional and is operated by Jal Sansthan.
• Out of the total 27 km distribution pipeline, 10 km has been laid and 17 km remains pending.
• The 9.7 km raising main ha |
| 4 |
Lalitpur |
20099699 |
LAKHANGER VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
69.99 |
0.30 |
0.30 |
0.00 |
69.70 |
69.99 |
Under Construction |
30.00 |
"• The scheme is located in Madawara Block and covers a single village under the Solar Dual Pump and New Retrofitting categories(left out village)
• The scheme is currently completely non-functional.
• The borewell has been completed, while installation of the pump, motor and solar system is still pending.
• The target has been set to make the scheme functional by 31 October."
|
| 5 |
Lalitpur |
20099714 |
JAITUPURA VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
68.30 |
6.56 |
6.56 |
0.00 |
61.74 |
68.30 |
Under Construction |
82.00 |
"• The scheme is located in Madawara Block and covers one village under the tubewell-based New Retrofitting category.(left out village)
• The target has been set to complete the scheme by 20 October
• pending bill is 5.42 lakhs.
• The proposed borewell has been completed, and the pump house has been constructed.
• Pump lowering and solar system installation are still pending.
• Against the target of 60 FHTCs, all 60 FHTCs remain pending.
• During the current week, 800 metres of pipeline has |
| 6 |
Lalitpur |
20099746 |
BADWAR VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
89.29 |
19.24 |
19.24 |
0.00 |
70.05 |
89.29 |
Under Construction |
85.00 |
"• The scheme is located in Madawara Block and covers one village under the tubewell-based New Retrofitting category.(left out village)
• Out of the total 4.50 km distribution pipeline, 3.00 km has been laid and 1.50 km remains pending.
• Pipeline testing is 100% pending.
• All 192 FHTCs are yet to be completed.
• The pump house civil work has been completed, while motor installation and solar system installation are pending.
• All 3 proposed borewells have been completed, and pipe lowering work |
| 7 |
Lalitpur |
20099749 |
KURRAT VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
135.10 |
18.40 |
18.40 |
0.00 |
116.70 |
135.10 |
Under Construction |
90.00 |
"• The scheme is located in Madawara Block and covers a single village under the Solar Dual Pump and New Retrofitting categories.(left out village)
• The agency has set a target to complete the remaining work by 15 October.
• in scheme have labiity of bill amount is 29.04 lakhs
• The tank structure has been completed, while painting work is pending.
• The entire 400 m raising main was completed last week.
• Out of the two pump houses, one has been completed and is functional, while construct |
| 8 |
Lalitpur |
20102391 |
PAPRO VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
21.18 |
0.00 |
0.00 |
0.00 |
21.18 |
21.18 |
Under Construction |
40.00 |
"• The scheme is located in Madawara Block and covers a single village under the Solar Dual Pump and New Retrofitting categories.(left out village)
• The target has been set to complete the scheme by 31 October.
• The proposed borewell has been completed.
• Installation of the solar dual-pump system is pending.
• Laying of 400 m of distribution pipeline is pending.
• All 22 FHTC connections are pending.
• The required materials have been received at the site.
|
| 9 |
Lalitpur |
20103935 |
Bansi Harshpur GOV water supply Scheme(Retrofitting) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1335.08 |
327.10 |
327.10 |
0.00 |
1007.98 |
1335.08 |
Under Construction |
70.00 |
"• The scheme is a Multi-Village Scheme (MVS) under New Retrofitting and covers 19 villages.
• Work has not yet commenced due to pending payment of ₹128.26 lakh against the scheme.
• The agency has stated that the remaining work will be completed within one month after receiving some funds against pending bills .
• One new tank has been constructed, with only painting and flooring work remaining
• Distribution pipeline work has been completed.
• Approximately 2,000 FHTCs are pending across |