| 1 |
Pratapgarh |
6823817 |
Jariyari PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
102.49 |
91.84 |
0.00 |
0.00 |
10.65 |
102.49 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 2 |
Pratapgarh |
6824800 |
Majhgawan pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
93.46 |
83.64 |
20.00 |
0.00 |
9.82 |
93.46 |
Under Construction |
26.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 3 |
Pratapgarh |
6824811 |
Puremadho Singh pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
73.00 |
65.57 |
25.00 |
0.00 |
7.43 |
73.00 |
Under Construction |
22.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 4 |
Pratapgarh |
6824815 |
Sadaha pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
150.45 |
134.51 |
61.90 |
0.00 |
15.94 |
150.45 |
Under Construction |
46.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 5 |
Pratapgarh |
6824820 |
Setapur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
122.67 |
108.82 |
20.04 |
0.00 |
13.85 |
122.67 |
Under Construction |
16.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 6 |
Pratapgarh |
6824823 |
Vikrampur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
175.42 |
156.57 |
0.00 |
0.00 |
18.85 |
175.42 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 7 |
Pratapgarh |
7617897 |
Dherahna QPV Scheme 2016 17 |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
113.41 |
101.39 |
0.00 |
0.00 |
12.02 |
113.41 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 8 |
Pratapgarh |
7889551 |
Bibiya Karanpur PWS Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
212.74 |
1.76 |
1.76 |
0.00 |
210.98 |
212.74 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued. 2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |
| 9 |
Pratapgarh |
8130426 |
Manaitapur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
139.37 |
0.26 |
0.26 |
0.00 |
139.11 |
139.37 |
Under Construction |
49.00 |
Work in Progress (T.well- 100%, Pipe Line- 70%, OHT-5%) |
| 10 |
Pratapgarh |
8130588 |
Raipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
232.72 |
0.41 |
0.41 |
0.00 |
232.31 |
232.72 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |
| 11 |
Pratapgarh |
8130726 |
Kadharpur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
189.74 |
12.85 |
12.85 |
0.00 |
176.89 |
189.74 |
Under Construction |
32.00 |
Progress of Work is slow (T.well- 70%, Pipe Line- 15%, OHT- 10%) |
| 12 |
Pratapgarh |
8130825 |
Lohang Patti Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
234.36 |
9.05 |
9.05 |
0.00 |
225.31 |
234.36 |
Under Construction |
33.00 |
Work of Progress is slow (T.well- 70%, Pipe Line- 40 %, OHT-30%) |
| 13 |
Pratapgarh |
8130860 |
Jagdishpur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
169.94 |
0.29 |
0.29 |
0.00 |
169.65 |
169.94 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |
| 14 |
Pratapgarh |
8131578 |
TALA SIRSABAD |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
193.90 |
0.49 |
0.49 |
0.00 |
193.41 |
193.90 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |
| 15 |
Pratapgarh |
8170500 |
BABA BELKHARNATH DHAM |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
227.13 |
10.31 |
10.31 |
0.00 |
216.82 |
227.13 |
Under Construction |
40.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |
| 16 |
Pratapgarh |
8193967 |
KHAJURI |
SRDWP |
Jal Nigam |
YES |
NO |
NO |
168.54 |
0.26 |
0.26 |
0.00 |
168.28 |
168.54 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |