| 1 |
Pratapgarh |
6824799 |
Madaipur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
130.28 |
116.55 |
78.39 |
0.00 |
13.73 |
130.28 |
Under Construction |
68.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 2 |
Pratapgarh |
7386081 |
Pure Rajju QPV Scheme 2015 16 |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
117.15 |
104.72 |
73.76 |
0.00 |
12.43 |
117.15 |
Under Construction |
60.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 3 |
Pratapgarh |
8170366 |
BHUWALPUR DOMIPUR |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
89.34 |
23.20 |
23.20 |
0.00 |
66.14 |
89.34 |
Under Construction |
70.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 31.10.2026. |