S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Pratapgarh 8130432 Dulhipur Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 154.77 56.08 56.08 0.00 98.69 154.77 Under Construction 83.00 Work in Progress (T.well- 100%, Pump House-70%,Pipe Line- 90%, OHT-60%,FHTC-190/474)
2 Pratapgarh 8130580 Amari Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 173.57 16.84 16.84 0.00 156.73 173.57 Under Construction 83.00 Work in Progress (T.well- 100%, Pump House-80%,Pipe Line- 80%, OHT-80%,FHTC-0/350)
3 Pratapgarh 8130665 Teliyani Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 201.13 71.76 71.76 0.00 129.37 201.13 Under Construction 81.00 Work in progress (T.well- 100%,Pump house-90%, Pipe Line- 40%, OHT-90%,FHTC-50/385)
4 Pratapgarh 8130687 Chaupai Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 172.51 54.85 54.85 0.00 117.66 172.51 Under Construction 85.00 Work in Progress (T.well- 100%,Pump House-90% Pipe Line- 85%, OHT-100%,FHTC-188/394)
5 Pratapgarh 8130701 Kadipur Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 225.17 90.62 90.62 0.00 134.55 225.17 Under Construction 80.00 Work in Progress(T.well- 100%, Pump House-90%,Pipe Line- 65%, OHT-95,FHTC-!80/416%)
6 Pratapgarh 8130712 Kishungarh Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 190.27 43.77 43.77 0.00 146.50 190.27 Under Construction 96.00 Major Work i.e T.Well, Pump House, OHT, Pipe Line, FHTC has been Completed. Development work of T.Well is in Progress which may be completed by 15/11/2026 after that Testing, Commissioning, of OHT, Pipe line Electro Mechanical equipments shall be completed within week and Scheme shall be made Operational by 20/11/2026
7 Pratapgarh 8131586 PURAB GAON NRDWP Jal Nigam YES NO NO 198.66 42.41 42.41 0.00 156.25 198.66 Under Construction 93.00 Work in Progress (T.well- 100%,Pump House-65% Pipe Line- 86%, OHT-95%,FHTC-182/643)