S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Prayagraj 20012559 Rajapur OLD RETROFIT Jal Nigam YES NO NO 213.30 12.25 12.25 0.00 201.05 213.30 Under Construction 80.00 The work Progress is Slow due to non-payment of an outstanding bill amounting to ₹ 32.72 lakh of contractor M/S Atul engineerings, Prayagraj. The following works are pending :- 2 Pump House, 13.3 KM distribution Line, 70% of Old OHT Repair Work, 436 House Connection and 40% of Boundry Wall Work.
2 Prayagraj 20106914 HANDIA RETRO 2 NEW RETROFIT Jal Nigam YES NO NO 136.01 0.00 0.00 0.00 136.01 136.01 Under Construction 78.00 Work progress in this Scheme. The following works are pending :- 1 Pump House, 8.26 KM distribution Line, 345 House Connection.