S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Sultanpur 8132007 LAUHAR DAXIN W/S SCHEME JJM (JAL NIGAM SCHEMES) Jal Nigam YES NO NO 452.75 166.18 166.18 0.00 286.57 452.75 Under Construction 88.00 Tubewell:- 2 nos :-Completed. Pumping Plant:- 1 Nos Completed, 1 nos Balance Pump house :-2 nos :- 1 nos complete(painting Pending),1 nos Civil Structure complete(door,window,electrificationand painting pending). Power Connection:- 2 nos completed OHT:- Top dome work Completed and vertical piping arrangement completed.hydrotesting plinth protection,drain and chamber work balance. Distribution system :- 29 km pipe line complete against 40.11 km pipe line FHTC :- 234nos completed against 1028