| 1 |
Bahraich |
8130812 |
PATHARKALA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
181.48 |
72.73 |
72.73 |
0.00 |
108.75 |
181.48 |
Under Construction |
85.00 |
The construction of the scheme's tank is in progress, and concreting of the top dome is currently completed. The target to complete the OHT work is 15th October, and the entire scheme is targeted for completion by 30th October. Due to limited space in the campus, the solar installation not started earlier Now the solar panels solar panel installation work in progress and the water supply will be started with in 10 days. |