| 1 |
Siddharth Nagar |
7854854 |
Marwatiya |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
151.19 |
68.21 |
68.21 |
0.00 |
82.98 |
151.19 |
Under Construction |
80.00 |
1️⃣Current progress of scheme: 1- OHT -90%,
2-D/S -70%
3-Tubewell- 100%
4- PH- 90%
5- Boundary wall- 90%
6- SQ- 85%
2️⃣Electrification work is pending for TW. Estimate received and deposited Rs 3.64 Lacs to UPPCL on Dated 27/08/2026
|
| 2 |
Siddharth Nagar |
7855172 |
Bhanpur Rani |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
288.34 |
105.77 |
105.77 |
0.00 |
182.57 |
288.34 |
Under Construction |
80.00 |
1️⃣Current progress of scheme:
1.OHT- 85%,
2.D/S -80%,
3.TUBEWELL- 100%,
4.PH- 85%,
5- Boundary wall- 90%,
6- SQ- 85%,
2️⃣Electrical connection is pending for TW, distribution system is in progress.
|
| 3 |
Siddharth Nagar |
7855176 |
Chaukhadha |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
391.13 |
192.94 |
192.94 |
0.00 |
198.19 |
391.13 |
Under Construction |
75.00 |
1️⃣Current progress of scheme:
1.OHT- 90%,
2.D/S- 70%,
3.Tubewell- 2 nos -100%
4. PH- 2Nos-100%,
5- Boundary wall- 90%
6- SQ- 85%
2️⃣Distrubution system is in progress. FHTC installation work is in progress.
|
| 4 |
Siddharth Nagar |
7855184 |
Semra |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
217.46 |
107.14 |
107.14 |
0.00 |
110.32 |
217.46 |
Under Construction |
80.00 |
1️⃣Current progress of scheme:
1.OHT -80%,
2.D/S- 80%,
3.Tubewell-100%,
4. PH- 95%
5- Boundary wall- 90%
6-SQ- 85%
2️⃣OHT and Distribution network work in progress. 3️⃣Partially water supply is active through Pump.
|
| 5 |
Siddharth Nagar |
7855186 |
Sohana |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
331.60 |
76.00 |
76.00 |
0.00 |
255.60 |
331.60 |
Under Construction |
65.00 |
1️⃣Current progress of scheme:
1.OHT- 85%,
2.D/S- 55%,
3.Tubewell-2no (1-100% and 2-0%).
4. PH- 2no (1-90% and 2-0%),
5- Boundary wall- 0%
6-SQ- 25%
2️⃣Electrical connection is pending for TW, 3️⃣Other works like eg : distribution system in progress.
|
| 6 |
Siddharth Nagar |
7855188 |
Unchadeeh |
WORLD BANK |
Jal Nigam |
YES |
NO |
NO |
295.89 |
155.84 |
155.84 |
0.00 |
140.05 |
295.89 |
Under Construction |
70.00 |
1️⃣Current progress of scheme:
1.OHT- 100%,
2.D/S- 55%,
3.Tubewell-100%,
4. PH- 100%,
5- Boundary wall- 100%,
6-SQ- 100%
2️⃣Distribution network and FHTC works are in progress.
|