S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Basti 7893806 Dewami GOV AES JE Schemes NRDWP Jal Nigam YES NO NO 277.32 125.72 125.72 0.00 151.60 277.32 Under Construction 76.00 1. Work started by firm, after notice for tender cancellation. 2. Rising Main Work In Progress. 3. Firm is trying to arrange 200 mm Dia DI-K-7 200 pipe.
2 Basti 7893813 Tenduwa AES/JE PWS Scheme NRDWP Jal Nigam YES NO NO 136.36 18.60 18.60 0.00 117.76 136.36 Under Construction 50.00 1. Due to land issue work could not be started. 2. Work started by firm, after notice for tender cancellation. 2. Pipe laying work In Progress. 3. Request for estimate has been submitted to UPPCL. 4. 6.88 Lacs bill uploaded on portal
3 Basti 7894118 KHADRA EMWQ NRDWP Jal Nigam YES NO NO 173.33 76.19 76.19 0.00 97.14 173.33 Under Construction 60.00 1. CB cancelled, Re-Tender Done. 2. OHT work is in progress.
4 Basti 8126991 Unji Mustakam PWS NRDWP Jal Nigam YES NO NO 285.57 53.84 53.84 0.00 231.73 285.57 Under Construction 76.00 1. Work started by firm, after notice for tender cancellation. 2. Pipe laying work In Progress. 3. Power connection is being carried out after receiving an estimate from UPPCL. 4. 34.52 Lacs bill uploaded on portal
5 Basti 8130025 Purshiya Gram Panchayat Water Supply Scheme NRDWP Jal Nigam YES NO NO 148.12 44.18 44.18 0.00 103.94 148.12 Under Construction 70.00 1. Work started by firm, after notice for tender cancellation. 2. Pipe laying work In Progress. 3. Request for a revised estimate has been submitted to UPPCL (Due to High Cost).
6 Basti 8130291 Omkuil GOV Water Supply Scheme NRDWP Jal Nigam YES NO NO 214.04 90.70 90.70 0.00 123.34 214.04 Under Construction 65.00 1. Work started by firm, after notice for tender cancellation. 2. Due to Local Dispute Power connection could not be carried out. 3. Due to water logging, corrently work is disrupted .
7 Basti 8178790 MAHADEWA GOV W/S (RETROFITTING) OLD RETROFIT Jal Nigam YES NO NO 111.82 24.16 24.16 0.00 87.66 111.82 Under Construction 76.00 1. Due to land issue (Court Case) OHT work could not be started. 2. OHT construction in progress on 2nd Land. 3. 30.6 Lacs bill uploaded on portal
8 Basti 8180316 Gotwa G.P. w/s Scheme (Retrofitting) OLD RETROFIT Jal Nigam YES NO NO 69.11 3.31 3.31 0.00 65.80 69.11 Under Construction 80.00 1. Due to outer ring-road construction in district distribution system has been affected. 3. Pump House construction in progress . 4. 30.96 Lacs bill uploaded on portal
9 Basti 20126168 Baisiya Kala G.P. w/s Scheme NEW RETROFIT Jal Nigam YES NO NO 177.21 29.84 29.84 0.00 147.37 177.21 Under Construction 90.00 1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL. 3. Power Connection Is in Progress. 4. 44.12 Lacs bill uploaded on portal
10 Basti 20126183 Jibhiyao G.P. w/s Scheme NEW RETROFIT Jal Nigam YES NO NO 201.04 46.50 46.50 0.00 154.54 201.04 Under Construction 90.00 1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL 3. Power Connection Is in Progress. 4.21.27 Lacs bill uploaded on portal
11 Basti 20126185 Amorah Khas G.P. w/s Scheme NEW RETROFIT Jal Nigam YES NO NO 384.20 94.39 94.39 0.00 289.81 384.20 Under Construction 90.00 1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL 3. Power Connection Is in Progress. 4. 64.71 Lacs bill uploaded on portal
12 Basti 20126187 Ashokpur G.P. w/s Scheme NEW RETROFIT Jal Nigam YES NO NO 341.59 57.23 57.23 0.00 284.36 341.59 Under Construction 90.00 1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL. 3. Transformer not energised Power Connection Is in Progress. 4. 61.67 Lacs bill uploaded on portal