S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Sant Kabeer Nagar 7401652 Alinagar PWS in JE/AEs affected Village NRDWP Jal Nigam YES NO NO 279.00 132.11 132.11 0.00 146.89 279.00 Under Construction 70.00 Remaining works-OHT 5%, Distribution System 75%, Pump House 5%, Boundrywall 10%, Pumping Plant 40%, Electrification 5%, FHTC 100% The work progress slow due to delayed payment
2 Sant Kabeer Nagar 7626726 MUKHALIS PUR NRDWP Jal Nigam YES NO NO 172.89 79.00 79.00 0.00 93.89 172.89 Under Construction 78.00 Remaining works- OHT 5%, Pump Hose- 5%, Distributionn system 5%, FHTC 40%, Boundrywall 100 %, Rising Main 100%. The work progress slow due to outstanding Payment 1. Bill Amount Rs. 3336315.00 due payment on date 16.03.2024 2. Bill Amount Rs. 308716.00 due payment on date 16.10.2025 Funds for electrification have been deposited by C&DS, and efforts are underway to secure the connection from the Electricity Department. Laying of 100 mtr. main pipeline and construction of boundrywall under disput
3 Sant Kabeer Nagar 7626822 MAHULI NRDWP Jal Nigam YES NO NO 377.92 239.05 239.05 0.00 138.87 377.92 Under Construction 70.00 Remaining works-OHT 5%, Risingmain 2nd 100%, Distribution System 20%, Pump House 2nd 30%, Pumping Plant 2nd 100%, Electrification 2nd 10%, FHTC 55% . The work delayed due to outstanding 1. Bill Amount Rs. 673089.00 due payment on date 08.07.2023 2 Bill Amount Rs. 749507.00 due payment on date 23.07.2024 3. Bill Amount Rs. 999231.00 due payment on date 12.09.2023
4 Sant Kabeer Nagar 7628100 KONI NRDWP Jal Nigam YES NO NO 279.38 191.85 191.85 0.00 87.53 279.38 Under Construction 65.00 Remaining works-OHT 10%, Raisingmein 100%, Distribution System 20%, Staffquarter 5%, Pump House 80%, Pumping Plant 100%, Electrification 100%, FHTC 65%, Boundarywall 60% . The work stop due to Pump house land issue by local public. 1.Bill Amount Rs. 75206.00 due payment on date 09.09.2025
5 Sant Kabeer Nagar 7892286 Katka GOV EMWQ PWS Schemes NRDWP Jal Nigam YES NO NO 263.30 44.46 44.46 0.00 218.84 263.30 Under Construction 30.00 Remaining works-OHT 100%, Raisingmain 100%, Distribution System 25%, Staffquarter 100%, Pump House 75%, Pumping Plant 100%, Electrification 100%, FHTC 63%, Boundarywall 70% . The work stop due to outstanding Bill Amount Rs. 2553698.00 due payment on date 15.04.2026
6 Sant Kabeer Nagar 7892839 Mahadewa G.O.V. Water Supply Scheme NRDWP Jal Nigam YES NO NO 165.22 24.64 24.64 0.00 140.58 165.22 Under Construction 30.00 Remaining works-OHT 80%, Raisingmain 100%, Distribution System 70%, Staffquarter 100%, Pump House 20%, Pumping Plant 100%, Electrification 100%, FHTC 73%, Boundarywall 80% . The work stop due to outstanding 1. Bill Amount Rs. 485866.00 due payment on date 15.12.2022 2. Bill Amount Rs. 587972.00 due payment on date 24.09.2024
7 Sant Kabeer Nagar 7893500 KARAUDA GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 135.58 12.85 12.85 0.00 122.73 135.58 Under Construction 25.00 Remaining works-OHT 100%, Raisingmain 100%, Distribution System 100%, Staffquarter 20%, Pump House 20%, Pumping Plant 100%, Boundarywall 100%, Electrification 100%, FHTC 100%. The work stop due to outstanding 1.Bill Amount Rs. 1182864.00 due payment on date 08.04.2024 2. Bill Amount Rs. 332982.00 due payment on date 24.09.2024
8 Sant Kabeer Nagar 7894072 PARASA SUKUL GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 149.66 1.33 1.33 0.00 148.33 149.66 Under Construction 60.00 Remaining works- OHT 30%, Pumphouse 5%, Pumping Plant 50%, Distribution System 11%, Electrification 100%, FHTC 40%, Boundarywall 100%. Eletrification work Estimate demonded by UPPCL. The work delayed due to outstanding 1. Bill Amount Rs. 1065396.00 due payment on date 16.10.2025 2. Bill Amount Rs. 999797.00 due payment on date 02.01.2026
9 Sant Kabeer Nagar 7894134 Dudhara EMWQ NRDWP Jal Nigam YES NO NO 246.62 119.91 119.91 0.00 126.71 246.62 Under Construction 75.00 Remaining works-OHT 5%, Pump house 30%, Distribution System 5%, Electrification 10%, FHTC 67%, Boundarywall 10% . The work progress slow due to delayed payment
10 Sant Kabeer Nagar 8027214 NANDAUR NRDWP Jal Nigam YES NO NO 365.92 120.32 120.32 0.00 245.60 365.92 Under Construction 65.00 Remaining works- OHT 10%, Raisingmain 100%, Staffquarter 100%, Pump House 1st 10%, Pump house 2nd 100%, Distribution System 32%, Tubewell 1st 10%, Tubewell 2nd 100%, Pumping Plant 1st & 2nd 100%, FHTC 67%, Boundarywall 100% . The work delayed due to outstanding Bill Amount Rs. 697216.00 due payment on date 20.03.2025
11 Sant Kabeer Nagar 8127436 GHOORAPALI NRDWP Jal Nigam YES NO NO 182.60 90.46 90.46 0.00 92.14 182.60 Under Construction 72.00 Remaining works-OHT 5%, Raisingmain 100%, Distribution System 33%, Staffquarter 5%, Boundrywall 10%, Pumphouse 5%, Electrification 100%, FHTC 100% . The estimate for more than enough revaised estimate demand by UPPCL dept. The work delayed due to payment
12 Sant Kabeer Nagar 8130009 TARYAPAR NRDWP Jal Nigam YES NO NO 182.00 66.58 66.58 0.00 115.42 182.00 Under Construction 87.00 Remaining Works- OHT 5%, Pump House- 5%,staffquarter 2%, Distribution system 5%, FHTC 45%, Pumping plant 30%, Risingmain 100%, Electrification 100%. Electric work indent issue to contractor by eletric devision against fund Deposited Rs. 251536.00 . The work delayed due to outstanding bill Rs. 2283803.00 Since 09.09.2024
13 Sant Kabeer Nagar 8130863 ON BILAIO NRDWP Jal Nigam YES NO NO 146.81 17.63 17.63 0.00 129.18 146.81 Under Construction 35.00 Remaining works-OHT 100%, Raisingmain 100%, Distribution System 25%, Staffquarter 25%, Pump House 25%, Pumping plant 100%, Electrification 100%, FHTC 70% . The work delayed due to payment
14 Sant Kabeer Nagar 8130880 GAYGHAT NRDWP Jal Nigam YES NO NO 151.85 11.98 11.98 0.00 139.87 151.85 Under Construction 15.00 Remaining works-OHT 100%, Distribution System 15%, Raisingmain 100%, Staffquarter 100%, Pump House 10%, pumping plant 100%, Electrification 100%, Boundarywall 70%, FHTC 50 %, The wok slow progress due to delayed payment
15 Sant Kabeer Nagar 8131643 BHAGAWATIPUR NRDWP Jal Nigam YES NO NO 184.87 37.63 37.63 0.00 147.24 184.87 Under Construction 55.00 Remaining works-OHT 5%, Raisingmain 100%, Distribution System 100%, Pump House 5%, Staffquarter 10%, pumping plant 30%, Electrification 50%, FHTC 100 %. Electric work indent issue to contractor in prosess by eletric devision against fund Deposited Rs .219371.00 . The work delayed due to outstanding 1. Bill Amount Rs. 256226.00 due payment on date 04.03.2024 2. Bill Amount Rs. 428842.00 due payment on date 19.04.2023 3. Bill Amount Rs. 458286.00 due payment on date 05.09.2024
16 Sant Kabeer Nagar 20094676 KUSAUNA KALAN GP WSS NEW RETROFIT Jal Nigam YES NO NO 181.30 3.60 3.60 0.00 177.70 181.30 Under Construction 5.00 Land Alloted on Date 06.08.2026 work stoped by local person during start of construction of boundry wall
17 Sant Kabeer Nagar 20094685 BARPARWA GP WSS NEW RETROFIT Jal Nigam YES NO NO 172.50 28.00 28.00 0.00 144.50 172.50 Under Construction 20.00 Remaining works-OHT 70%, Raisingmain 100%, Distribution System 100%, Staffquarter 100%, Pump House 100%, pumping plant 100%, Electrification 100%, FHTC 100 %, Boundarywall 100%. The work delayed due to payment of Rs. 619614.00 Since 07.08.2025
18 Sant Kabeer Nagar 20094694 GIRDHARPUR GP WSS NEW RETROFIT Jal Nigam YES NO NO 228.20 16.24 16.24 0.00 211.96 228.20 Under Construction 17.00 Remaining works-OHT 70%, Raisingmain 100%, Distribution System 100%, Staffquarter 100%, Pump House 100%, pumping plant 100%, Electrification 100%, Boundarywall 100%, FHTC 100 %. The work stop due to outstanding bill Rs. 927147.00 Since 26.08.2026
19 Sant Kabeer Nagar 20094795 BARHYA THATHAR GP WSS NEW RETROFIT Jal Nigam YES NO NO 451.42 97.90 97.90 0.00 353.52 451.42 Under Construction 62.00 Remaining works-OHT 50%, Distribution System 11%, Staffquarter 100%, Pump House 10%, pumping plant 100%, Boundarywall 100%, FHTC 49 %, Electrification 100%, . The work delayed due to Bill Amount Rs. 3590755.00