| 1 |
Sant Kabeer Nagar |
7401652 |
Alinagar PWS in JE/AEs affected Village |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
279.00 |
132.11 |
132.11 |
0.00 |
146.89 |
279.00 |
Under Construction |
70.00 |
Remaining works-OHT 5%, Distribution System 75%, Pump House 5%, Boundrywall 10%, Pumping Plant 40%, Electrification 5%, FHTC 100%
The work progress slow due to delayed payment |
| 2 |
Sant Kabeer Nagar |
7626822 |
MAHULI |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
377.92 |
239.05 |
239.05 |
0.00 |
138.87 |
377.92 |
Under Construction |
70.00 |
Remaining works-OHT 5%, Risingmain 2nd 100%, Distribution System 20%, Pump House 2nd 30%, Pumping Plant 2nd 100%, Electrification 2nd 10%, FHTC 55% . The work delayed due to outstanding
1. Bill Amount Rs. 673089.00 due payment on date 08.07.2023
2 Bill Amount Rs. 749507.00 due payment on date 23.07.2024
3. Bill Amount Rs. 999231.00 due payment on date 12.09.2023 |
| 3 |
Sant Kabeer Nagar |
7628100 |
KONI |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
279.38 |
191.85 |
191.85 |
0.00 |
87.53 |
279.38 |
Under Construction |
65.00 |
Remaining works-OHT 10%, Raisingmein 100%, Distribution System 20%, Staffquarter 5%, Pump House 80%, Pumping Plant 100%, Electrification 100%, FHTC 65%, Boundarywall 60% . The work stop due to Pump house land issue by local public.
1.Bill Amount Rs. 75206.00 due payment on date 09.09.2025
|
| 4 |
Sant Kabeer Nagar |
7894072 |
PARASA SUKUL GP WATER SUPPLY SCHEME |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
149.66 |
1.33 |
1.33 |
0.00 |
148.33 |
149.66 |
Under Construction |
60.00 |
Remaining works- OHT 30%, Pumphouse 5%, Pumping Plant 50%, Distribution System 11%, Electrification 100%, FHTC 40%, Boundarywall 100%. Eletrification work Estimate demonded by UPPCL. The work delayed due to outstanding
1. Bill Amount Rs. 1065396.00 due payment on date 16.10.2025
2. Bill Amount Rs. 999797.00 due payment on date 02.01.2026 |
| 5 |
Sant Kabeer Nagar |
7894134 |
Dudhara EMWQ |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
246.62 |
119.91 |
119.91 |
0.00 |
126.71 |
246.62 |
Under Construction |
75.00 |
Remaining works-OHT 5%, Pump house 30%, Distribution System 5%, Electrification 10%, FHTC 67%, Boundarywall 10% . The work progress slow due to delayed payment |
| 6 |
Sant Kabeer Nagar |
8027214 |
NANDAUR |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
365.92 |
120.32 |
120.32 |
0.00 |
245.60 |
365.92 |
Under Construction |
65.00 |
Remaining works- OHT 10%, Raisingmain 100%, Staffquarter 100%, Pump House 1st 10%, Pump house 2nd 100%, Distribution System 32%, Tubewell 1st 10%, Tubewell 2nd 100%, Pumping Plant 1st & 2nd 100%, FHTC 67%, Boundarywall 100% . The work delayed due to outstanding
Bill Amount Rs. 697216.00 due payment on date 20.03.2025 |
| 7 |
Sant Kabeer Nagar |
8127436 |
GHOORAPALI |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
182.60 |
90.46 |
90.46 |
0.00 |
92.14 |
182.60 |
Under Construction |
72.00 |
Remaining works-OHT 5%, Raisingmain 100%, Distribution System 33%, Staffquarter 5%, Boundrywall 10%, Pumphouse 5%, Electrification 100%, FHTC 100% . The estimate for more than enough revaised estimate demand by UPPCL dept. The work delayed due to payment |
| 8 |
Sant Kabeer Nagar |
8131643 |
BHAGAWATIPUR |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
184.87 |
37.63 |
37.63 |
0.00 |
147.24 |
184.87 |
Under Construction |
55.00 |
Remaining works-OHT 5%, Raisingmain 100%, Distribution System 100%, Pump House 5%, Staffquarter 10%, pumping plant 30%, Electrification 50%, FHTC 100 %. Electric work indent issue to contractor in prosess by eletric devision against fund Deposited Rs .219371.00 . The work delayed due to outstanding
1. Bill Amount Rs. 256226.00 due payment on date 04.03.2024
2. Bill Amount Rs. 428842.00 due payment on date 19.04.2023
3. Bill Amount Rs. 458286.00 due payment on date 05.09.2024 |
| 9 |
Sant Kabeer Nagar |
20094795 |
BARHYA THATHAR GP WSS |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
451.42 |
97.90 |
97.90 |
0.00 |
353.52 |
451.42 |
Under Construction |
62.00 |
Remaining works-OHT 50%, Distribution System 11%, Staffquarter 100%, Pump House 10%, pumping plant 100%, Boundarywall 100%, FHTC 49 %, Electrification 100%, . The work delayed due to
Bill Amount Rs. 3590755.00 |